Here are the works that await Belgraders in the near future (PHOTO)



[ad_1]

THERE WILL BE A MAIN BUS STATION AND THE ROAD WORKERS ARE WORKING AT FULL STEAM: Here are the jobs that await the Belgraders in the near future (PHOTO)

Photo: Facebook Prinstcreen, Goran Vesić

EOGRAD – I visited the workers who are carrying out works on the roads of Block 42, that is, the new bus station. These works are being carried out to widen the roads around the new bus station. The road widening works are being carried out rapidly, in parallel with the construction works of the F800 heating pipe due to the need to relocate the heating pipe located at the location of the future bus station, the deputy mayor wrote from Belgrade, Goran Vesić, on his official Facebook page.

A part of the heating pipe has been completed on Yuri Gagarin Street, so today another 2000 m2 of the last layer of asphalt was made, whose right-hand road of Yuri Gagarin Street next to the future bus station with 4 lanes circulation was completely completed. On Monday, the remaining 700 m2 will be paved at the junction next to the market, so that before December 16. Traffic will open on the new 4-lane right road along OTC and BAS from the descending ramp from the bridge in Ada to Marko Hristić Street.

At the same time, works are being carried out on the path of the Anti-Fascist Struggle in both directions. On the road closest to the OTC, works are being carried out on the remaining 140 m of heating pipes, which will be finished at 12:12 p.m., and on the road closest to the BAS, the asphalt layer works are being carried out on the road and sidewalk, which will be finished at 19.12.

As of December 17, the works will begin on the second Yuri Gagarin road in the direction of Gazela, where work will be done on the construction of the fecal sewer and the expansion of the lane for the bus niche.

These works and the asphalt works of the Antifašističke borbe street along the OTC are scheduled to be completed as of December 31, 2020 and the traffic will return in full mode. After the New Year, works will be carried out on the construction of a siphon sewer connection in Marko Hristić.

The works began in mid-June 2020, the agreed value of the works is around 278 million dinars without VAT, and the agreed term is 270 days. The works are expected to be completed in March 2021.

(Kurir.rs/Facebook)


delivery courier

Author: delivery courier



[ad_2]