CNI Investment Director, Adrian Cefalan, He spoke about the status of the project. The team’s new stadium Dynamo could have a capacity of 33,000 seats, and the cost of the works will be 100 million euros.
Regarding the Dinamo Stadium, we specify that CS Dinamo initially transferred to CNI the location of the current Velodrome for which the public procurement process began and the contract for the preparation of the pre-feasibility study and the feasibility study was signed.
100 million euros for Dinamo’s new stadium, which could have 33,000 seats
Now solutions have been identified for the construction of a new stadium in a larger rugby and football area. In this sense, CNI asked CS Dinamo to draft a new concept note and the design issue related to the new land area, as well as to obtain a new urban planning certificate.
After sending this documentation, the CNI will issue the order to start the design services for the pre-feasibility study and subsequently the feasibility study in order to approve the technical-economic indicators.
We specify that, after discussions with CS Dinamo, we want to build an arena with a capacity of approximately 33,000 seats, but the final capacity will result after the preparation of the pre-feasibility study and the feasibility study, relative to the land area, urban planning, as well as the requirements imposed by ISU on escape routes.
The works at the Dinamo stadium will last between 18 and 24 months
Thus, considering cost standards, with an approximate capacity of 33,000 seats, an approximate cost of 90-100 million euros is estimated.
We specify that until the actual execution of the works a series of steps must be carried out, namely, the preparation and approval of the feasibility study, the issuance of a government decision that approves the technical-economic indicators, the completion of the public procurement procedure of design and execution. ), preparation of the technical project and obtaining the building license. After issuing the order to start the execution works, we estimate a period of 18-24 months “, declared Adrian Cefalan, for Digi Sport.
For this season Dinamo rented the National Arena. However, the “dogs” are forced to play in the “Pit” while the Arena grass is replaced.
Dinamo Stadium has a capacity of 15,032 seats. It was opened in 1952 and renovated in 2007.