UPDATE 19.42 CNAIR officials presented an official point of view on the issue reported in Bacau:
Regarding the images that appeared in the public space regarding the damage to the road in VO Bacau that appeared after the traffic, CNAIR makes the following clarifications:
– The damage was due to a manufacturing error in a joint on the bridge km 3 + 150, right side.
The most desired extra-salary benefits at the best cost for your company: Up Breakfast Breakfast card with 0 issuance costs + Regina Maria medical subscription at the best market price: from 3 euros / month / employee. Get the offer HERE!
– As soon as this problem was detected, the Contractor signaled the respective area and carried out the remediation works in an emergency manner, so that at this time it is safe to drive along the entire length of VO Bacau.
– Considering that, until the final reception of the works, the builder still has to carry out said meetings, the traffic in this objective is carried out with a speed restriction of 90 km / h ”.
Initial novelty:
Representatives of the CNAIR confirm the situation and say that situations of this type are still encountered and that traffic restrictions are imposed until the entire stretch is completed.
“It can happen. It was not a well, it was a purpose in VEO Bacau. Those things happen. We gave this part of the road before precisely because it is requested by many people. If until recently, the policy was to do the reception throughout the road and people waited a long time, you know how they said about roads, which are a museum, this year it was decided to start a little earlier.
There are some restrictions until the whole lot is finished but it is possible to circulate in a civilized way.
It happened that the purpose was not well done. We remake it, we put restrictions. You can pass. If 10,000 cars passed yesterday and one passed them, we regret this situation, they will probably be compensated, but the important thing is that they are driving ”, explained Manuela Dumitru, CNAIR spokesperson for Ziare.com. .
The representative of the institution also specified that the businessman decided together with CNAIR to start the road earlier.
However, it appears that the person who reported the incident was not the only unfortunate one.
The owner of the company who intervened in the drivers’ call for help says that he attended six interventions, in total, and in all cases the drivers had to change both wheels and tires.
“Of the six interventions we had, five drivers had to change both their rims and tires. On one of the cars, a new rim cost around 800 euros,” said Nastase Teodor, owner of the service. for the Observatory.
Last week, Prime Minister Ludovic Orban congratulated the builders who made the Bacau detour, as they announced that the section of track with a highway profile will be able to be given to traffic between November 27 and December 2, although the The deadline for the completion of the works was January 2022.
In addition, Transport Minister Lucian Bode boasts of the money the state paid for the Moldavian Highway. “I would like to clarify one more thing, because they accused us of financing this goal, of allocating very little money in 2020. I want to tell you that I have paid 467 million so far in a year in a year” Lei, compared to 126 paid by those who preceded us. Therefore, we pay all the intermediate payment certificates and we will absolutely pay to the last leu whatever we have to pay for this goal, ”said Bode.
The Moldavian Highway was inaugurated on December 2. The authorities have announced that, for now, traffic will be restricted to 90 kilometers per hour.
The works amounted to 668.33 million lei (excluding VAT), and the contractor that took charge of the execution of the road section was Asocierea Spedition UMB SRL – Tehnostrade SRL. The source of funding is represented by non-reimbursable European funds. The length of the entire work is 30,843 km and consisted of the construction of seven bridges, eight passages, a road junction, seven roundabouts and a small parking lot.
Read also:
VIDEO How are the first kilometers of the highway in Moldova. The job was completed a year ahead of schedule