Metrorex clarifies the opening of traffic on the M5 Drumul Taberei metro line, after the reception at the end of the works.
According to a press release, Metrorex announces that commissioning procedures are underway. These consist of the configuration of the systems from the test phase to the operation phase for road safety facilities and passenger information, cargo, closed circuit television and communications.
Likewise, the spaces are delivered-received from the construction company to the Metrorex teams, which will ensure with the 900 employees the operation, circulation and maintenance in 3 shifts for all specialties, including commercial service and train driving service .
Another necessary activity is to transfer the security objectives in stations and interstates, from the security companies of the constructors to those that have a contract with Metrorex.
The day before commissioning with passengers, all public spaces are assigned by the manufacturer’s cleaning companies to those contracted by Metrorex.
For the inauguration, the last activity consists of replacing the trains used for the tests with those prepared in the depot for passenger traffic.
According to Metrorex, the configuration of the loading system allows access with cash and a bank card to the turnstiles. The POS terminals are acquired by the bank that provides technical support and are in the configuration process so that the sale is available in addition to cash and bank card at the ATM. At the vending machines, cards can be paid for in cash.
Payment by bank card will be implemented as soon as possible together with the supporting bank. It is necessary to achieve a stable communication solution that involves both the configuration and the installation of equipment and encryption keys.
Metrorex is also concerned with ensuring the GSM signal and the comfort facilities that this service offers to all users. Thus, during this period, mobile operators have completed the installation of underground communication networks and have made the last adjustments to the equipment for optimal coverage of the voice and data communication signal for metro passengers.