Extremely worrying situation at the construction site of the Transylvania Highway, where almost no work is being done on the lot between Chețani and Câmpia Turzii. According to the information obtained by Digi24, the heads of the Infrastructure Company are looking for solutions to pay directly to Straco subcontractors, which is the only hope that the works will continue on the 16 kilometers of the highway.
From the images presented by the Pro Infrastructure Association it can be clearly seen that the construction site is almost abandoned.
maker, Insolvent Romanian company Straco has had no people on site for some time and its subcontractors are unpaid. Therefore, they have stopped working or will soon.
According to NGOs passionate about infrastructure, currently only the embankment side subcontractor, the Romanian company Marcotim, is still mobilized, but in the absence of payments and supply of materials from Straco, it will soon be unable to provide consumables on site and pays salaries or taxes. . You have to collect more than 10 million lei from Straco.
PAccording to information obtained by Digi24, those responsible for the Infrastructure Company are looking for solutions to pay directly to Straco’s subcontractors.
Works for the Chețani-Câmpia Turzii lot began in May 2016 and should have already been completed. However, after 4 years, his stage reached only 36%.
The value of the investment is about 280 million lei. The money comes, as in most large infrastructure projects, from Brussels.
The Road Company is hesitant to make a firm decision regarding Straco’s contract for the Chețani-Câmpia Turzii lot because the same company is working on the Domnești passage on the Capital Beltway.
Director of the road company: we are still with them on one condition
Mariana Ioniță, General Director of CNAIR: “This motorway sector is one of the remainder. It is an old contract and we intend to have it in circulation next summer. Our main concern at the moment is, in addition to mobilizing on site, fair and timely payment of contractors and suppliers of construction materials.
The company has made great efforts to support and support the Straco company since it is a Romanian company and we are still with them on one condition: pay the subcontractors and material suppliers on time.
We want to be able to pay subcontractors directly.
Our deadline is next summer. We can organize a new public procurement procedure if we do not achieve a commitment with the Straco company ”.
Read also:
Drone images. What does a nearly abandoned lot on the Transylvanian Highway look like?
Publisher: Georgiana Marina