Šimonytė on Astravas AE: Everything from start to finish is haunting



[ad_1]

“Everything there, from start to finish, is alarming. Our main line and main argument from the beginning has been that we are talking about an insecure structure and even more so in that country the information is absolutely critical since we can never trust any official information, such as any documentation that was missing just before the commissioning. planned operation of the plant. “I. Šimonytė told LRT radio.

“The incidents that are taking place at the site are worrying and only encourage more active measures so that there are no reflections in the development of this plant and what is being done is stopped as much as possible,” he added.

According to I. Šimonytė, some questions about methodologies among the Baltic countries remain unanswered.
“The key question is who finances this whole farm. There is a law in Lithuania that absolutely prohibits the purchase of electricity produced by this power station in any form. Then there is the big question of how an item can function that simply does not generate a flow of energy. We have had a discussion here in recent weeks with the current Minister of Energy about what the various mirages mean, however, regarding the methodology that was agreed upon and that perfectly complied with the laws and interests of Lithuania, and those questions remain unanswered, “I told LRT radio. Šimonytė.

After the CN Astravo exploded with several voltage transformers in one of the units connected to the generator, the CN Astravo stopped generating electricity on Sunday, tut.by reported Monday.
“The safety of the reactors is not affected by such incidents. But if there is a fire in the transformer, the commissioning of the Belarusian nuclear power plant for industrial operation will have to be postponed for the time necessary to repair the equipment,” writes belatom .by.

Vitaly Novicki, spokesman for the Belarusian Ministry of Emergency Situations, assured that the incident at the Belarusian nuclear power plant was not within the competence of his agency, because “at 200% there was no fire there.”

Eduard Svirid, director of the Information Center of the Belarusian nuclear power plant, asked to wait for an official comment.

Litgrid System Management Center on November 3. 11.06 am after recording data showing electricity production at the Litgrid nuclear power plant from 11.38 am. establish 0 megawatts of bandwidth for the flow of commercial electricity from Belarus.

Belarus is building a 2,400 MW nuclear power plant near the city of Astrava, which is 50 kilometers from Vilnius. The plant will be made up of two 1,200 MW power units.

Lithuania criticizes the project which, in the opinion of the country’s representatives, is being implemented in violation of nuclear safety requirements.

No part of this publication may be reproduced without the written permission of ELTA.