In August 2018, it was announced that a new kindergarten would be built in Bajorai, in the northern part of Vilnius. Vilnius municipality then signed 3.92 million. A one-euro contract with Irdaiva, one of the largest construction companies in the country.
However, the contract with the contractor UAB Irdaiva was terminated by agreement of the parties on September 17, 2019 “due to changed factual circumstances.” 15 minutes Alina Kovalevskaja, Senior Advisor on Education of the Vilnius City Municipality Administration, reported.
15 minutes recalls that bankruptcy proceedings against Active Construction Management (formerly Irdaiva) were initiated in October last year. On October 28, the Vilnius Regional Court granted the request of the head of Active Construction Management, Vito Lopinis, to initiate bankruptcy proceedings against the company.
Photo by Saulius Žiūra / Kindergarten.
According to A.Kovalevskaya, during the implementation of the project there was a need to change the technical project due to the construction of a thermal route through a newly formed parcel, state forest land.
“The parcel itself was formed after the date of receipt of the building permit, so it is necessary to design an alternative renewable energy source within the parcel and to redesign all engineering networks that are designed on state forest land, as well as adjust all project components accordingly. “
According to A.Kovalevskaya, 2019. On August 1, a contract was signed with the author of the project, Panevėžio statybos trestas, regarding the correction of the project and the detailed plan.
“Corrections to the detailed plan and project have been prepared. It is planned to announce a tender for construction works in 2020. Mid-July “, 15 minutes she reported.
We remind you that the kindergarten in Bajorai had to be completed and that the children already had to go to it in the 2019-2020 school year. It is true that Povilas Poderskis, the director of the Vilnius administration, did not promise that this would be the case.
“However, unfortunately we have to admit that all the projects implemented by this company (Irdaiva – BNS) are constantly delayed. It is difficult to trust their promises, so it is not easy to promise residents something,” BNS explained.
It was previously announced that the planned kindergarten on Bajorai Road will be equipped with rooms for 14 groups with auxiliary rooms, two elevators and one elevator, driveway, trails and playgrounds. A transformer station, engineering networks and other works will also be built.
District residents were surprised to see that a store would be built next to the planned kindergarten – information signs had already been erected.