Drivers are angry at the Liepkalnis intersection in Vilnius: traffic jams, no signs



[ad_1]

Pavilnys is also clogged

Povilas from Vilnius constantly drives at this intersection, and it has yet to be rebuilt, when congestion formed here during rush hours and during repair work, when cars were circulating in newly installed rings. However, Monday’s drive to the city center from Gurių Street in Kalnėnai was longer than ever.

“It just came to our notice then. Not only did everything around this intersection come to a halt, but also Pavilnys, Kalnėnai. Traffic was supposedly released through a newly formed intersection, but there are not even signs – you are driving and all of a sudden, you no longer know which lanes you can turn into.

And pedestrians no longer know how to behave at all. Standing and looking, because even the crosswalks are not marked. You simply have to go, fearing that the tractor will not get in the way. With the type of wheelchair out there, probably no parent would risk crossing the street, ”Povilas said Monday morning.

It hasn’t been that bad yet. Not only did everything around this intersection stop, but also Pavilnys, Kalnėnai.

In the tunnel, as Povilas noticed, there are very few cars driving directly from the Minsk highway to Žirnių street, everyone wants to turn Liepkalnio street towards the city center or towards Rudamina, Šalčininkai. Over the weekend, drivers complained that the green light was on for only a few seconds, so congestion was guaranteed.

Already on Sunday, many drivers tried to reach the city center on Black Road after changing the organization of traffic at this intersection. Due to the huge traffic, there have also been traffic jams of kilometers, the traffic is also blocked by the repair works that are being carried out on this street.

Congestion at the Liepkalnis intersection

Congestion at the Liepkalnis intersection

Allowed “partially”

Last week, the Vilnius city municipality released information that “the grandiose reconstruction of the intersection of Liepkalnio, Žirnių streets and Minsk highway has reached the finish line,” so the organization of the workplace traffic: the new tunnel and the viaduct are partially permitted.

“Traffic lights will also begin operating at the intersection, which will distribute traffic flows by destroying temporary roundabouts. As final works still need to be done at the intersection, drivers must pay attention to traffic lights, road signs and markings. horizontal and follow the KET rules, ”the Vilnius city municipality wrote in a press release last week.

Photo by Julius Kalinskas / 15min / Liepkalnis and Minsko pl.  intersection

Photo by Julius Kalinskas / 15min / Liepkalnis and Minsko pl. intersection

According to the municipality, in May. At the beginning of the year, around 85% of Works over 32.5 million. euros.

End of september

“As of May 8 or 9. Traffic will be partly possible through the newly built tunnel and viaduct, but there will be temporary restrictions at the new two-level intersection due to completion of the works: installation of barriers, painting of tunnel and viaduct walls, installation of rails bike, paving etc. Immediately after the traffic reorganization, it is planned to install pavements eliminating the current temporary roundabout at Liepkalnio str.

One week later, on May 15. – Another traffic correction will be made and traffic will be allowed with new sidewalks Liepkalnio str. at the site of the old roundabout. Then, the works will be carried out in another Liepkalnio str. side by side, ”the report said.

Photo by Julius Kalinskas / 15min / Liepkalnis and Minsko pl.  intersection

Photo by Julius Kalinskas / 15min / Liepkalnis and Minsko pl. intersection

A full resumption of traffic at this intersection is scheduled for mid-July, and the project will finally be completed and delivered on September 9.

Precisely because the project is not finished yet and the actual opening is scheduled for September 9, according to the municipality, and there is a reason why there is no shortage of traffic interruptions at this time: works will continue here for about a month. , so there will be restrictions.

The reconstruction is being carried out by the supplier groups UAB Fegda and UAB Tilsta. The cost of the project is about 40 million. euros. Part of the funds for the implementation of the project are allocated by the Vilnius city municipality, about 22 million. euro – Government.