Changing the order is important for those who intend to connect to the electricity grid and other electricity consumers.



[ad_1]

“We strive to make regulation of the electricity services market simple and user-friendly.

This simplified procedure is especially relevant for companies, for which the rapid implementation of infrastructure projects is important, residents who want to install the power plant and all consumers who want to connect electrical equipment to electrical networks, increase the capacity of power, relocate power lines or wiring. ”Says Energy Minister Dainius Curvature.

The amendments establish the conditions and procedures under which electricity consumers may organize and contract contractors for the installation, reconstruction, wiring and relocation of electricity distribution networks in cases where the distribution networks impede the construction of structures or by other reasons.

According to the current procedure, these works can normally only be carried out by the operator of the electrical distribution network, indicating the final price of the works to consumers. The new procedure provides the opportunity to find contractors who will do the job cheaper and faster themselves, if they meet the established requirements and have the necessary skills and experience.

Consumers will also be able to organize the installation of the electrical distribution networks required for their needs, if they meet the established conditions, have projects prepared according to the connection conditions issued by the distribution network operator, the newly connected power will exceed the 500 kW and the Contractor will pay more than 10 percent less than the contractor selected by the operator. This will allow greater flexibility in carrying out work without waiting for the distribution network operator to do it.

Likewise, in order to adequately regulate the reserved capacities in the electricity networks, the period of validity of the distribution network operator’s project has been set (now undefined). The project is expected to be valid for 1 year after coordination with the distribution network operator or while the connection service contract is valid.

It is recalled that since 2021. February 1 Provisions came into force that reduce the price of reconstruction and relocation of overhead power lines of 0.4-10 kV and overhead cable lines with more than 20 years of age by up to 50 percent, when network relocation is carried out by the distribution network operator on demand. of a person.

Also starting in 2021. February 1 The changes came into effect for electricity generation consumers seeking to connect their electrical equipment to distribution networks; generation consumers will have to pay 50 percent of the real cost of the work for connecting electrical equipment (until then they paid 100 percent of the price). ). These changes harmonize connection prices for new consumer electrical equipment and encourage the population to become electricity-generating consumers.