Povilas Poderskis for half a million euros fine for the repair of the Liepkalnis crossing: we still save



[ad_1]

He was sanctioned but did not terminate the contract.

The SCL declared illegal the actions of the municipality in the evaluation of the suppliers’ offers and annulled the decisions of the courts of first instance and of appeal, but did not annul the purchase contract illegally entered into for the protection of the public interest, therefore assigned 500,000 LTL to the municipality. a fine of EUR. This SCL decision is final and is not subject to appeal.

The highway construction company Panevėžio keliai appealed to the court the decision of the municipality to reject its tender and declare Fedga and Tilsta the winners of the tender.

Consequently, the city will have to pay the fine, but works will continue with the same two companies that won the contest in 2019 in the summer. The contract, the amount of which is 31 million. The reconstruction of this intersection was signed in 2019. November 8, Liepkalnio, Žirnių and Minsko pl. Fegda and Tilsta, winners of the contest to rebuild the crossing, promised to complete the works in 2 years.

Photo by Saulius Žiūra / Works Liepkalnio, Žirnių st.  and Minkslo pl.  at the intersection in September

Photo by Saulius Žiūra / Works Liepkalnio, Žirnių st. and Minkslo pl. at the intersection in September

Will pay but don’t understand

When asked to comment on how he evaluates the SCL’s decision, P. Poderskis, director of the Vilnius municipal administration, did not wrap too many words in cotton: “no one will be able to complain anymore.

By choosing, in our opinion, the bid of the legal winner, we saved 1.5 million. euros and a lot of time. The choice is still financially correct and the fine will have to be paid.

By choosing, in our opinion, the bid of the legal winner, we saved 1.5 million. euros and a lot of time. The choice is still financially correct and the fine will have to be paid. It is true that we will continue to consider the possibility of adjusting the fine to the contractor. “

According to P. Poderskis, the works at this junction, which caused and continue to cause many difficulties for drivers during the repair, are progressing rapidly. “The reconstruction works are going well. The contractor works on time, everything is fine-tuned and the object itself will open on time,” he said.

Photo by Saulius Žiūra / Works Liepkalnio, Žirnių st.  and Minkslo pl.  at the intersection in September

Photo by Saulius Žiūra / Works Liepkalnio, Žirnių st. and Minkslo pl. at the intersection in September

There will be a two-level intersection

It is estimated that by mid-October more than 23 million jobs have been completed. euros.

Read more about the SCL’s decision and the comments of the lawyers of the company Panevėžio keliai here: LTL 0.5 million was allocated to the Vilnius government for violations in the tender for the reconstruction of the Liepkalnis intersection. a fine of EUR.

After the reconstruction is complete, part of the four traffic lanes, the more than 800-meter-long Žirnių street and the Minsk highway will be located in the tunnel, with a regulated intersection of Liepkalnio street installed above it. It will be a viaduct over 23 m long and 78 m wide.

During the reconstruction of these streets and intersections, it is planned to have about 2.2 kilometers of roads, rebuild 1.5 kilometers of water supply, 918 meters of sewer networks, lay 8.3 kilometers of lighting cables and install about 5 , 3 kilometers of rainwater networks.