[ad_1]
The new electric power operator in the region, Afinia, reported that it will carry out network adaptation work this weekend, so that some neighborhoods of Cartagena and municipalities of Bolívar will be affected by the interruption in service.
Schedule for Saturday, November 21
In Cartagena
* Company technicians will work on the Bosque 3 circuit from 8:40 in the morning until 3:00 in the afternoon, affecting the La Quinta neighborhood.
* Improvements will also be made from 7:00 in the morning to 3:00 in the afternoon in the sector of Carrera 81 to 84 between streets 22 and 37, San Fernando neighborhood.
In Arjona
* Afinia technicians will continue with the construction of a new circuit for Arjona, for this reason poles and other elements will be installed in the Gambote 5 circuit, which will cause interruptions in sectors of the municipal seat, between 9:00 am and 5:00 am: 30 pm
– The neighborhoods of Arjona that will be without service are: July 20, November 5, Arjona, Buenos Aires, Calle El Coco, Ceibal, Delicias, El Carito, El Carmen, El Cementerio, El Mercado, El Olivo, El Poly, El Silencio, The Zoo, Station, The Station, Jose María Córdoba, La Esperanza, Las Margaritas, La María, La Paz, The Plaza, Las Brisas, Santa Rosa de Lima, Las Cabras, Las Nieves, The Plots, New Blower, Porto Belo, Porvenir, San José, San Roque, Santa Lucia, La Cruz Sector, Soplaviento, Tank, Turbaquito and La Peña Urbanization.
In Marialabaja
* Preventive technical pruning will be carried out in Marialabaja from 7 am to 3:30 pm, which will impact the entire municipality, including its townships and sidewalks. The Sabanas de Mucacal, San Antonio, Labarces and Boca Cerrada districts in the jurisdiction of San Onofre, Sucre will also be without electricity.
(Read: These neighborhoods of Cartagena will not have drinking water tomorrow).
Schedule for Sunday, November 22
In Cartagena
* Intervention will be made to the Bocagrande substation, therefore the service will be interrupted in the circuits that supply the tourist sector of Bocagrande, Castillogrande and El Laguito.
The programming begins at 7:30 in the morning and will end at 6:00 in the afternoon, time in which specialized personnel will work on the power transformers and other equipment of the substation.
The Manager of Afinia in Bolívar Norte, Eder Buelvas Cuello, indicated that to complete this maintenance a last technical shutdown is required, scheduled for the end of November.
(Read: Cartagena will last weekend rain: CIOH).
In Bayunca
* Corrective and preventive maintenance will be carried out at the Bayunca substation, between 5:00 a.m. and 8:00 a.m. The works imply the disconnection of the Bayunca 1, 2, 3 and 4 circuits, so Santa Rosa will be without power , Villanueva, a sector of Arenal, Santa Catalina and Clemencia, including their townships and sidewalks.
* In Cartagena the Ibiza del Mar Urbanization, Terranova Urbanization, Barcelona de Indias Urbanization and the townships of Puerto Rey, Arroyo de las Canoas, Arroyo de Piedras, Manzanillo del Mar and Tierra Baja, among others, will be left without service.
[ad_2]