When will the Padma Bridge open? | World | DW



[ad_1]

Bridges Minister Obaidul Quader said the remaining work, including rail connectivity, would take at least 10 months. However, the Padma Bridge project manager Shafiqul Islam said: “There is no possibility of launching the Padma Bridge in 2021. We are six months behind We were supposed to be where we are today in June 2020, but we did it six months later. After finishing the work on time, we promised to open the Padma Bridge in June 2020 But that is no longer the case. There is more work to be done. “

He said it was not possible to say when the train would start. The railway line will be connected to the bridge. But the railroad will be necessary on both sides of the bridge.

Shafiqul Islam said: “We will be able to sit down with the contractors about the upcoming bridge work and inform them within a month when the Padma bridge will open to traffic.” The opening of bridges on both sides of the railway will not be blocked.

The remaining works on the main bridge include carriageway slabs, rail slabs and installation of super-beams. Slab pitch casting, lighting, lamppost installation, etc.

Trains will pass through the bottom of this concrete and steel bridge and vehicles will pass over it. As a result, the shape of the bridge will be 7 stories. In three years, two months and 10 days, 41 spans were installed in 41 piers of the Padma Bridge. And the cost of this project has tripled the initial cost The total budget for the bridge is now 30,193.39 crore The bridge is being built with Bangladesh’s own funds after the World Bank and development partners withdrew their loans claiming corruption. The bridge has so far cost Tk 24,115.02 crore The work has been completed, a little more than 72 percent

With the launch of the Padma Bridge, 21 districts in the southwest of the country will be directly connected to the rest of the country, including the capital Dhaka. 6 will come under rail communication More than four million people will benefit directly from it. And it will have a positive impact on the country’s economy. The World Bank said the bridge would increase GDP by two percent. But economist CPD said. Khandaker Golam Moazzem thinks: “It may not be due to the increased cost of the bridge. However, it will have a positive impact on the economy. Now that the southern region is in connectivity, an economic zone will be formed” Because there is gas and port facilities “He said. There has been a delay due to complications with the World Bank There was a problem with the governance of the river, Kovid is another problem It seemed to us that there was still an opportunity to make spending a little more reasonable But the sooner it opens, the better “.

He believes that the bridge will increase domestic and foreign investment Asian countries that want to use the port of Pigeon and Mongla can use it The bridge will connect the Asian highway and the trans-Asian railway network, which will play an important role in regional connectivity.

China Railway Major Bridge Engineering Company Limited (MBEC), a Chinese contractor, is working on the bridge. Sino Hydro Corporation 6, another Chinese company, has done the river governance work

Bangabandhu Sheikh Mujibur Rahman Rector of Digital University Prof. Munaj Ahmed said: “Padma bridge is not complex design bridge Simple span trust bridge 6 Bangladesh engineers already have knowledge about it It is also taught here But their specialty is the enormity 6 We did not have technology What to bring 6 And as such a large project has been implemented with its own funds, the technology has been transferred It was not possible with foreign financing This is another great advantage beyond our bridge. In the future, our engineers will be able to build these bridges themselves. “

According to him, “the only challenge for the bridge was its foundation due to the fast flowing river and silt. The bridge will be used for hundreds of years.”

Take a look at the photo gallery from November 22 …



[ad_2]