Broken from Dhaka in an hour



[ad_1]

Mawa in 40 minutes

To see the current status of the Dhaka-Mawa-Bhanga Expressway, I went out by motorcycle through the Greater Hanif flyover at 10:30 am last Tuesday. This part of the overpass merges with Dolairpara. The Dhaka-Mawa-Bhanga Highway started from there.

As you walk towards Jurain, you will see that a boat-shaped pedestrian bridge is being built. However, under the part of Jurain, the situation now is dire. Stopping the bus in the middle of the road and picking up passengers, parking on the side of the road, non-mechanical vehicles and pedestrians slow down the speed of vehicles.

After crossing the Postagola Bridge, he found himself in the Hasnabad part of Keraniganj. Pedestrians stopped their vehicles and ran across the street. He jumped across the island from the road. The bliss of the unbroken road can be found from Ikuria, part of Keraniganj. However, the maximum speed limit on this route is 60 km. Although that is not acceptable.

Although the bus was supposed to stop at a specific location, it was not accepted at the Abdullahpur stop. Passengers are picked up by stopping the bus in the middle of the road, although there is a place to stop the bus. Human transporters were also seen soaring up the highway as the broken highway fence melted. Accidents also occur on freeways due to disobedience and reckless driving. In the Srinagar area, workers were seen repairing a structure damaged in the accident.

[ad_2]