5400 meters of the Padma bridge are visible, the remaining 5 spans



[ad_1]

With the installation of section 36 on the main bridge, five thousand four hundred meters of the Padma bridge can be seen. And if five spans are installed, the remaining 650 meters will be visible. Span 36 was placed on the second and third piers on the Mawa side of Munshiganj on Friday morning.

According to engineers, section 38 is scheduled to be installed on November 11. Executive Engineer at Padma Bridge Dewan. Abdul Quader The daily star“The One-B stretch was installed on the main bridge around 9:42 am today,” he said. It took less than two hours to do it.

Engineers also said the Tian-e floating crane left Mawa Construction Yard yesterday with a span. It takes longer to arrive due to the navigability crisis. After anchoring the span it was not enough to place. So on the second day the stretch was laid.

Shafiqul Islam, director of the Padma Bridge project, said that construction work on the Padma Bridge was halted for four months due to the corona situation and flooding. Four tranches have been successfully placed according to the October target. There are also plans to install four sections this month.

Section 38 (2-C) on November 11, section 36 (1-A) on November 16, section 39 (2-D) on November 23, section 40 (2-E) on December 2 and last section 41 (2-) on December 10. F) will be placed.