If the weather is favorable and there are no technical problems, the 36th section ‘2-C’ of the Padma Bridge can be installed on Thursday. The span will be placed at posts number 9 and 10 at the end of Mawa in Munshiganj.
Bridge engineers say that if there is time, spans can be installed on certain posts today. Otherwise, the span installation work will be completed on Friday morning. When span 36 is installed, 5,550 meters of the bridge will be visible.
Executive Engineer of the Padma Bridge (Main Bridge) Dewan. Confirming the information, Abdul Quader said the floating Tiain-e crane left the Kumarbhog construction yard at 9 am Thursday for the 36th 150-meter stretch. If the opening has time after reaching the post, if there is no technical problem in the next process and if the weather is favorable, the opening will be placed the same day. However, if there are any obstacles, the span will be installed on Friday.
The installation of this section began within 7 days after the installation of section 36. On November 8, section 36 was placed at poles 2 and 3 on the Mawa side. There are still 5 openings so that the entire bridge is visible.
The bridge authorities also said that after the installation of section 36, section 38 (section 1-A) on posts No. 1 and 2, section 39 (section 2-D) on posts No. 10 and 11 on November 23, and section 40 on posts No. 11 and 12 on December 2. (Tranche 2-E) and on December 10, Tranche No. 41 (Tranche 2-F) will be placed on posts 12 and 13. All tranches are in the Mawa construction yard.