[ad_1]
The Taipei city government planned to build a music and book center at the former AIT site on Xinyi Road, but it was started by Kuomintang member Yu Shuhui. The original project budget was just $ 2.8 billion, but it increased from $ 5.3 billion to $ 8.1 billion, questioning the mayor’s promise to “save money.” Ke Wenzhe looked. “Apple News” obtained exclusive information. Ke Shi held a review meeting every two weeks. Cultural director Cai Zongxiong was still unable to give details of the budget. He also replied, “It’s been reported before,” and made Ke slam the table furiously five times. He still couldn’t quell his anger after taking antihypertensive drugs and said “someone must give up being responsible for this.”
After the AIT (American Association in Taiwan) moved into the new Neihu building, the city planned the original base to cover the audiographic center. In the general question on the 6th, member Yu Shuhui questioned the project’s budget from 2.8 billion yuan to 8.1 billion yuan per ping. Average construction cost is higher than Taipei Pop Music Center and New Taipei city general map. The mayor is a fake person who says “save money”. What is outrageous is that the Office of Cultural Affairs sent the budget to parliament without Ke’s knowledge, so Ke, who was preparing for the forum consultations, had no idea. I could only promise to review and list the budget increase in two weeks.
◆ Cai Zongxiong didn’t know clearly, but he countered that Ke P was so angry that it was incoherent.
It is understood that at the mayor’s meeting on the morning of the 24th, Culture Director Cai Zongxiong and Section Chief Guo Peiyu were invited to report on the case. However, the Office of Cultural Affairs stated that the PCM (Technical Service Providers) oversaw the entire budget, but the site was unable to provide detailed funding. After that, Cai Zongxiong, also suspected of cross-examining Ke, replied that “this has been reported before. “
The so-called PCM is a manufacturer of technical services. Government units will entrust a PCM team for almost all project payments to check whether the construction manufacturer’s budget is reasonable.
It is noted that Ke has rarely bothered at the morning meeting recently for self-cultivation. After the report on the same day, Yin Ke was unaware of the 8.1 billion figure. Furthermore, the Office of Cultural Affairs was unclear at the meeting, causing Ke to jump like thunder. He thumped the table furiously during the meeting.
◆ Ke got up and hit the table three times, swallowed the medicine, and then hit the table twice.
According to informed helpers, Ke stood up and hit the table three times and started cursing. His speech was a bit incoherent, and then his blood pressure skyrocketed. To control his emotions, Ke quickly took “blocking agent B”. In the end, he still couldn’t beat the table twice. He threatened that “this matter has been sent to parliament and someone should resign responsible for this matter.” At the final meeting, the Office of Cultural Affairs asked the Office of Cultural Affairs to list the detailed prices and then explain them to parliament.
Staff said this matter was discussed by councilors in the blanket question two weeks ago. The Office of Cultural Affairs has a long time to prepare, but the content of the report is still insufficient. This is considered to be the main reason for the mayor’s anger. The current sound map has an exact budget of 81.7. Ko did not oppose this figure, but there must be a base, otherwise the city government will have a hard time defending it and will be criticized by then.
Cai Bingkun, the deputy mayor who oversaw the case, candidly said that the case was indeed discussed on the 24th. Cai Zongxiong gave a detailed explanation of the motive behind the whole case, but what is the 8.1 billion article? You are required to make a clear classification before contacting the council. As for whether Ke Wenzhe was angry at the table that day? Cai Fan asked the media, “Who told you about this part? Then you should ask him.” He still decides the matter.
◆ Cai Zongxiong refutes the dispute and states that he will confirm the budget with Ke in March.
“Apple” asked Cai Zongxiong and replied that there was no dispute that day, but there were some discussions. The Budget and Cultural Affairs Office confirmed with the mayor in March that it was based on a demand to return from a visit to northern Europe. Once the decision was made, the PCM team from the Department of Water Resources was asked to estimate the amount that is finally delivered to the Office of Cultural Affairs and the Office of Education to prepare the annual budget. A sound map is a library, which is compiled by the Office of Education, and the other Cultural Office of the Music Center is responsible for the compilation.
Cai Zongxiong explained that the cost of sound maps is not relatively high. There are Beiliu, Weiwuying, Gaoliu and Taichung opera houses inside. These costs range from 270,000 to 340,000 per ping, but the sound map is only 306,000.
As for why is the mayor angry? Cai didn’t want to talk any more and just said: “This is not very convenient for me … this part … The mayor may want to know some details about the financing of the construction of our art place.”
Currently, the audiovisual demand plan is ready for your announcement. Cai Zongxiong emphasized that the part of the budget will depend, of course, on the results of the parliamentary deliberation. There may be a revised quantity or surface adjustments. Everything will be announced online after the final decision. (Chen Sihao / Taipei Report)