This year the intersection of Žirnių and Liepkalnio streets in the capital will be completed, the works of the Lazdynai basin will be renewed, the construction of the Tolminkiemis gymnasium and the Antakalnis hospital block will begin.
Povilas Poderskis, director of Vilnius city administration, also mentioned the management of various parks and the Neris embankments on the Kalba Vilnius website, naming the biggest and most important projects this year in the capital.
Intersection of Žirnių and Liepkalnio streets
Photo 1
“It is probably the largest project in terms of volume this year. It is a two-level intersection and after its construction there will be a high yield towards the Minsk side. It is part of the complex development of the region around this intersection, as there are airport areas nearby, Girteka is planning to build its headquarters and Teltonika is planning a big project. Project of impressive size: a flyover like a serious metropolis. Completion of construction is scheduled for the fall, “says P. Poderskis.
Hazelnut basin construction
Photo :: 2
“This year we plan to restart the Lazdynai basin project, which makes us sad. 2017 a contract was signed, but funding for the project was cut from the state and this resulted in the contractor getting relatively low prices and apparently not having evaluated all of them. The risks. He did not try to build that building anyway, and even the joint venture partners who joined were unable to build it for the promised price, “says P. Poderskis.
According to him, the project has now been adjusted and a new works contract has been announced.
photo :: 10left
“If it works smoothly, we will have a new contractor in February. Currently, 40% of the construction is done, but it all depends on the attitude of the contractors. If they judge that the work has been done well, they will have 60% done, but if they judge that the work has been done poorly, there will be more ”, says P. Poderskis.
According to him, the degree of risk can vary. The representative of the municipality assures that he will be able to recover the price difference from the UTE partners who have previously participated in the tender.
“Overall, the project shouldn’t be more expensive and, most importantly, we have a reliable contractor,” says Mr. Poderski.
According to him, the work could start this spring and last more than a year.
“It just came to our knowledge then. Suppliers also compete on time in purchasing, so they have to say so,” says P. Poderskis.
Construction of the Tolminkiemis gym
Photo :: 3
“With Do Architects, we have a project after the architecture competition, we have announced the competition and we hope to have a contractor in a month. So that process will start this year. The school, which was built in Balsiai through a concession, has passed time, this school in Pilaitė will also pass time, it will set the tone for all the other schools in the region. It seems to me that the priority of the municipality should be the infrastructure for education ”, says P. Poderskis.
According to him, the construction of the school is expected to be completed in 2022. September.
“Construction will be quick and the project is adapted to allow us to pour concrete and factory elements. The entire project and its management will be digital. In terms of speed, this should be a very fast project, but we’ll see what it will look like in practice. This is very new for the public sector ”, says the director of the city administration.
Construction of the operating room at Antakalnis Hospital
Photo :: 4
“In terms of medicine, the largest construction will be in the operational unit of the Antakalnis Hospital. This hospital is very old, it has been built by many Lithuanian doctors. After the expansion, the old block will be able to adapt for other uses after minor repairs. However, it has been standing without repairs for 50 years, with only cosmetic corrections, and the flow of operations is uninterrupted: around 10,000 of them are carried out per year. Therefore, it is necessary to build a new building where these services will be concentrated. We will definitely expand these services in Vilnius, because they are lacking, the availability is not enough, ”says P. Poderskis.
According to him, the capital is also beginning to consider the construction of a new infectious hospital.
Public space on Vingrių street
embedgallery :: https: //foto.vz.lt/embed/741? location =
“We are planning to install a promenade near the MO Museum, a spring will open from the old Vingrii well. There will be more space for cafes and people,” says P. Poderskis.
It has been announced that going down the stairs from Mindaugo street towards the Old Town, it is planned to start the renovation of the territory in spring.
It is planned to install sidewalks, stairs, green areas, children’s playground, memorial, instead of the parking lot Vingri spring springs will be opened, which will flow through waterfalls. An observation deck will be installed on the stairs from Mindaugas to Vingrių Street.
The term of the works is 8 months and the works are worth 1.4 million. The euro will be provided by Conresta.
Installation of a Japanese garden
Photo :: 5
“The planned garden in Šnipiškės will be managed according to Japanese tradition, its nature will be very well cared for. There will be both a bridge and a tea house; we want to create a recreational area surrounded by business centers and new residential neighborhoods,” says P Poderskis.
According to him, tens of thousands of square meters of new buildings are currently being built in Šnipiškės, so the population is constantly growing and will continue to grow. The park will be open to all, it will not be paid as previously planned.
“Construction will start this year, we already have a contractor. We will prepare the area this winter and construction will begin in warm weather.” Eikos statyba “has experience in building parks, so it is likely that no major problems will arise there”, says P. Poderskis.
Reconstruction of the renovated garden
Photo :: 6
According to the director of the administration, Eikos statyba is also completing the reconstruction of the Reformed Park.
“We will be able to enjoy it this spring. In fact, the theme of the opening has more to do with quarantine than with work. Everyone’s wishes and thoughts are integrated into the project, it will be a space not only for those who live around, but also for everyone else, ”says P. Poderskis.
Reconstruction of embankments of Neris
Photo :: 7
According to P. Poderskis, the reconstruction of the last two terraces on the right bank of the Neris River is currently being completed, which will be ready for use in the summer. This will complete the layout of the Žirmūnai bridge section and the Forum Palace.
“A tender has been announced for the contractor on the left side, from the A. Goštautas bridge to the Šilo bridge. It is an incredibly long stretch and although there will not be many solutions, there will be more landings, terraces, places for business, and they will be enabled lanes for pedestrians and bicycles, ”he says.
The municipality also plans to install a warehouse in front of the Palacio de Deportes: design, obtain the building license and sell it for business development.
“We will see if it will be a café, boat rental. We would like the works on the left side to start this year, at least from the A. Goštautas Bridge to the White Bridge,” says the director of administration.
Energy Museum
Photo :: 8
According to P. Poderskis, the King Mindaugas Bridge development works are currently being completed along with the Museum of Energy and Technology.
“The problem is that it is done together with the Hilton hotel project developed by Kauno saulėtekis, which is now on hold. However, it seems that the museum should open in summer ”, says the director of administration.
Central business district
Photo :: 9
“The development on the right bank of the Neris does not end, despite what we see now built. There we will have a new building for Ibrahim, a new building for Eika, a building designed by Daniel Libeskind, the Business Stadium project will be fully developed and new buildings will be erected instead of the parking lot in front of the municipality. Several skyscrapers will have to be developed near Lvovo street, etc. Until full maturity, there will still be 10-15 years of development, then the planning of southern Vilnius will end and it will start to expand, ”says P. Poderskis.
According to him, the execution of the detailed plan of the center of Vilnius and the construction project of the right bank of the Neris prepared by the architect Algimantas Nasvytis in 1964-1965 continues in this way.
“Although the concept of a central business district is a bit old-fashioned in western cities, it is far from being such a powerful center of attraction in Vilnius as to say ‘finished’. Apart from the buildings mentioned, the issue of transport is also not It is resolved, a viaduct through the Iron Wolf Ring, perhaps even a tram or vice versa, perhaps the narrowing of the Avenida de la Constitución and additional construction ”, considers the director of the administration.