Original caption: Sihui East Station on Subway Line 1 will resume operations today and is expected to reach “18-18” early next year
Beijing News Express (Reporter Pei Jianfei) October 1, BeijingUndergroundThe operation project to connect Line 1 and Batong Line was started, and the first phase of the project has been successfully completed. Starting today (October 8), Line 1 East Sihui Station resumes normal operations. The reporter learned that in the next step, the subway department will suspend the construction of the Sihui Station on Line 1. The operation of Line 1 and Batong Line is expected to be completed early next year.
At 9 a.m., passengers transfer to Sihui East Station.Beijing News reporter Pei Jianfei
This morning, the reporter saw at Sihui East Station on Line 1 that construction had been completed. The first batch of four sets of turnouts connected Line 1 and Batong Line together, and the train resumed normal operation. This also marks the successful completion of the first phase of the “One to Eight Connection” project. The connection operation of Line 1 and Line 8 will enter the countdown phase.
“Because the construction site is too narrow, a lot of large-scale equipment cannot be used, which brings certain difficulties to the project implementation, but we are all on schedule.qualityIt does. “Beijing MetroEngineering Managementlimitedthe companyviceGeneral ManagerXu Tiankun told reporters that due to the short time available for online operations, in order to ensure that the project nodes go on schedule, each step in construction must be accurate to the minute. “We have transformed the communication signal system, the power supply system and the switch system. At present, the entire system has been rebuilt and basically the railway and electrical connections have been made.proofAnd a dynamic signal test and a full line graph test were carried out, providing a prerequisite for the next “step one to eight” step. “
The subway line 1 train is about to enter Sihui Station. The oblique track next to the vehicle is the newly added 4 sets of turnouts. Beijing News reporter Pei Jianfei
Xu Tiankun said that after the resumption of operations, Line 1 and Batong Line will continue to operate in the original way, and passengers will still need to transfer at Sihui Station or Sihui East Station. In addition, the transformation of the Line. 1 and the Batong Line is very complicated.Systems engineer, In addition to the hardware system,ServiceThe system must also be updated, such asstationScreen, guideLogo, Broadcasting system, television on board, etc. Therefore, a series of projects will be carried out in the future, and the construction of Sihui Station on Line 1 will be suspended. “Passengers can transfer at Sihui East Station on Line 1. It will have a great impact. on everyone’s travels. “
It is understood that according to the current plan and construction progress, by the end of this year, the reconstruction project will realize the track on the hardware, and the full operation of Line 1 and Batong Line is expected to be completed. early next year.
Beijing News reporter Pei Jianfei
EditBai Shuang corrects Zhao Lin
(Source: Beijing News)
(Editor in charge: DF398)