Original Title: Shijiazhuang Centralized Isolation Point Builder: -10 ℃ Construction, 200 Integrated Houses Installed
Beijing News reporter Wu Jiaoying
At first, I was actually more concerned about whether the workers would have some emotions out of fear of the epidemic, but I didn’t expect everyone to be enthusiastically signing up and actively participating in the relief project.
On the night of January 14, the centralized isolation point in Guying Village, Zhufutun City, Wenzheng Street, Zhengding County, Shijiazhuang City, Hebei Province, was under urgent construction. Guo Xin, the project secretary of the China Second Construction Bureau’s third company, who assisted in the construction of the project, said in an interview with Beijing News that the on-site staff currently work around the clock. of the day and his project team will complete the construction of more than 600 sets of insulated containers.
18 square meters of bathroom facilities in each room
Beijing News:Tell me about the project you are helping to build.
Guo Xin:We are currently building a centralized isolation point in Shijiazhuang Zhengding. Our Second Office and Third China Construction Company have five construction projects in Shijiazhuang. Since the outbreak of the epidemic in Shijiazhuang, our construction personnel have been isolated in their respective project departments. After being tasked with assisting in the construction of the centralized isolation point of Zhengding in Shijiazhuang, we quickly conducted two nucleic acid tests to construction aid personnel and rushed to the construction site.
Over the next 2 days and 2 nights, we will continue to do insulated container assembly installations and complete the assembly of more than 600 insulated container sets. Each integrated house covers an area of 18 square meters, with a bathroom, complete water and electricity pipes, and the components of the house can be assembled in one day.
Beijing News:When were you tasked with building an isolated integrated house in Shijiazhuang? How long did the team take to complete the assembly?
Guo Xin:We received the construction assistance task at 7:30 this morning, at which time we brought together 36 managers and 114 workers in one hour. Today, the company has successively dispatched some additional workers and managers to support.
Beijing News:How many employees do you currently have on the site? How is construction progressing?
Guo Xin:There are about 180 people on our project site. We started building container houses around 11am. So far, more than 200 built-in house sets have been completed, including more than 30 built-in sets that have all the complete support team.
The integrated room of the isolation point must ensure tightness
Beijing News:Were you surprised when you received the construction assistance assignment?
Guo Xin:In fact, it is not an accident. It is not surprising, because we have been carrying out works in Shijiazhuang, and we also know that the current epidemic situation in Shijiazhuang is relatively serious. We may need to build a large refuge hospital or a centralized isolation point like Wuhan, so we are always prepared. The accident was due to the actual mission arriving very suddenly and forcing us into the battle quickly so I was quite nervous.
At first, I was actually more concerned about whether the workers would have some emotions out of fear of the epidemic, but I didn’t expect everyone to be enthusiastically signing up and actively participating in the relief project.
Beijing News:Have you performed similar construction tasks before?
Guo Xin:We have also installed container style houses before, but basically when we were doing construction projects our own staff used them for accommodation and office near the construction site. This is the first time that such a large centralized isolation point has been built.
Beijing News:What are the special requirements for the construction of central isolation point projects?
Guo Xin:The built-in house for insulation is definitely much higher than the requirements for the offices and accommodation places we built in the past. First of all, we must ensure the tightness of the isolation room to avoid virus infection. Second, we have to choose the best and safest materials, all of which are higher than national standards.
Construction workers change masks and measure temperature every 3 hours
Beijing News:Are there difficulties in the current construction?
Guo Xin:At present, our main difficulty is that the materials for integrated housing are not enough and the supply is a bit scarce, in addition, time is short and the tasks are heavy. We will install on site 24 hours a day and strive to complete isolation point construction as soon as possible to ensureCommon peopleLife safety.
Beijing News:What is the work environment like on the construction site?
Guo Xin:The atmosphere in the place is relatively difficult. Now the temperature in Shijiazhuang is minus 10 ° C. The weather is very cold. Our workers can only work and eat outside and have no time to sleep. However, not everyone has complaints and I am very proud to be involved in such a construction project.
Beijing News:How do on-site construction personnel do a good job of preventing epidemics?
Guo Xin:We are currently divided into 14 groups with 10 people in groups, each with two managers. All personnel on site change their masks every three hours, measure their temperature at the same time, and are always attentive to the temperature and health of the workers.
Netizens shouted in the live comment area: I can participate in the construction!
Last night, Beijing News broadcast the process of building the Shijiazhuang quarantine point and received many messages from netizens barrage: