Original title: The Beihai LNG receiving station fire accident caused 5 deaths, caused by the construction of the tank’s front platform

According to the “Beihai Release” news on November 3, at approximately 11:45 on November 2, the pipeline from the front platform of tank 2 of the State Pipe Network Group Beihai LNG Co. LNG receiving station dock. , Ltd. in the port of Tieshan was under construction. When a fire broke out, the fire went out at 11:55. After continuous search and rescue, so far, of the 9 people working at the site, 5 people died, 1 lost contact and 3 people were seriously injured.

According to the above news, after the accident, the two-level party committee and the city government quickly organized the fire rescue, emergency management, market supervision, public safety, health and other related departments on the scene to fully cooperate with the company in rescue and disposal. The State Pipe Network Group dispatched experts to the site to conduct the safety assessment of the equipment and facilities. The Autonomous Region Health Commission organized medical experts to come to Beihai to help treat the injured. At present, the search and rescue of personnel, the treatment of the injured and other work are being carried out in an intense and orderly manner, and the cause of the company’s construction accident is still under investigation.

A fire broke out at the Beihai LNG receiving station on November 2, China News Service

Beihai LNG (liquefied natural gas) receiving station is the first LNG receiving station project in southwest China. It is located in Nangangchi Petrochemical Operations Area, Tieshangang District, Beihai City. Construction started in July 2013 and test operation started in March 2016. The LNG receiving capacity is 6 million tons / year, and the long term can reach 10 million tons / year. According to information when the project was put into production, the main target markets for the project are Guangxi, Beihai, Qinzhou, Nanning, Laibin, Liuzhou and Zhanjiang and Maoming in Guangdong province, as well as Yunnan and Guizhou.

The receiving station was originally affiliated with the Sinopec Group and was handed over to the National Pipeline Network Group more than a month ago.

On September 30, the State Pipeline Network Group held a signing ceremony for the delivery of assets and the handover of the operation of the oil and gas pipeline network. According to the agreement, the State Pipeline Network Group and China National Petroleum Corporation, Sinopec, China National Offshore Oil Corporation, China Chengtong, China Guoxin and Social Security Foundation The asset transaction agreement and the capital increase and share expansion agreement signed by China Insurance Investment Fund, China Investment International and Silk Road Fund will come into effect at 24:00 on the same day, and the National Pipeline Network Group will take over the relevant oil and gas pipeline foundations that originally belonged to the top three oil companies. Facility (business) assets and personnel are officially connected to the network for operation.

The National Pipeline Network Group explained the cause of the accident in a notice issued on November 2 that at 11:45 a.m. on that day, Beihai Liquefied Natural Gas Co., Ltd. was conducting inspections and repairs of 2 LNG storage tanks. and there was a fire. Process, start sprinkler extinguishing system, open flame has gone out at 12 o’clock.