Complete the third stage of the ventilation task Universal Studios theme park has functions as a dining room for tourists-Qianlong.com.cn



[ad_1]

Source Title: Complete the third stage of the Ventilation Task. The Universal Studios theme park serves as a tourist dining room.

On December 10, Beijing Gas Group announced that the Universal Studios theme park, the sub-center of Beijing, completed the third phase of ventilation. This gas vent project is reported to be huge in volume, involving seven thematic scenic spots. A total of approximately 7 kilometers of gas pipelines, 29 gas meters and more than 430 devices need to be ventilated and 9 surge tanks will be activated.

In 2020, as the Universal Studios theme park scenic area has fully entered the project acceptance stage, the natural gas ventilation task will begin immediately. The project includes a central canteen, eating streets and hotels, as well as radiant heating and multiple flame effects. The third branch of Beijing Gas Group has proceeded in an orderly manner with the Universal Studios natural gas construction project. In July, it successfully completed the first Universal Studios theme park ventilation project, namely the Ventilation Operation of the Logistics Support Area. In October, it successfully completed the ventilation operation of its power center and city avenues. .

The competent person in charge of the third branch of Beijing Gas Group stated that to ensure the smooth acceptance of the third phase of the natural gas project, the company established a project working group to formulate a special ventilation operation plan, strengthen the link with the design unit and the construction unit, and strictly control the construction. Project quality and progress, strengthen the coordination and cooperation of the company’s internal departments and base units, effectively open all the nodes of the gas construction link, and smoothly promote the implementation, acceptance and ventilation of the project.

According to the competent person in charge of the third branch of Beijing Gas Group, the natural gas project for acceptance and ventilation can be roughly divided into two parts, indoor and outdoor. On December 3, the external ventilation operation was officially launched. As the operation site was affected by construction in the park and the vehicles could not enter, the personnel in charge of the outer pipeline had to walk from one side of the operation site to the other for acceptance of the pipeline engineering. , providing assurance for the next step of full line ventilation. When the information verification and confirmation voices from the doors came from the walkie-talkie, the ventilation operation officially began.

The staff first carried out the lock shaft drilling work to confirm that the lock shaft opening and closing conditions met the requirements, and then gradually increased the pressure in the pipeline to ensure good tightness of the pipeline and ensure there are no gas leaks. When the command headquarters issued the ventilation replacement order, the various release points began to be occupied … “Report! Sampling is qualified.” The news of the last qualified release point sampling, I saw the nozzle after the sampling and ignition test, and the light yellow rose. The outside line ventilation operation was completed successfully.

On December 4, the unpacking of the exterior surge tank and interior ventilation officially began. At the operation site, employees have to pull the cord, delimit the area of ​​operation, place fire extinguishers, check whether the gas meter and gas equipment information is consistent with the general ledger information and make prior preparations to the operation. Once the installation specifications are met, the tightness test is performed. When the outer surge tank was purified, the outer piping was rated for voltage stabilization and the inner piping was rated for airtightness testing, headquarters issued a vent order.

“Now start the replacement of the interior ventilation …” Beijing Gas employees perform the replacement of the ventilation. After the bladder sampling is scored, the equipment ignition test and gas equipment scrubbing are carried out. After close and uninterrupted cooperation and continuous operation, a total of 15 gas meters were aired that day, including special effects at the Transformers stage, heating boilers and tourist dining areas.

Perform tightness tests on gas lines, remove blanking plate replacements, release samples, ignition tests and adjust ranges … Personnel keep going back and forth between multiple indoor locations and outdoor work areas, all links are closely coordinated, continuous operation, after three days At 18:00 on December 5, the third branch of Beijing Gas Group successfully completed the safe ventilation of all gas equipment.

The construction of the Tongzhou Cultural Tourism Zone, the sub-center of the city of Beijing, is understood to be one of the key projects of the Beijing Municipal Government. The Beijing Universal Studios theme park natural gas project is one of the key contents of natural gas construction in the Tongzhou Cultural Tourism Zone, the sub-center of Beijing city. After the completion of the stage ventilation project, the Universal Studios theme park can be equipped with radiant heating, special effects for entertainment facilities and dining room for tourists.