Original Title: Fully Respond to the High Pollution Climate! The Ministry of Ecology and Environment sent 100 working groups to involve these industries. Source: Beijing Daily
In order to make every effort to deal with the high pollution climate, the Ministry of Ecology and Environment sent 100 supervision and assistance working groups to Beijing-Tianjin-Hebei and the surrounding areas on March 1, focusing in steel, coking, cement,glass(2024, 56.00, 2.85%) and other key industries, provide supervision and assistance for emergency response to heavily polluted weather conditions.
As of March 14, the supervision and assistance working group had inspected 4,030 companies at the site and found 770 problem companies and 1,055 various atmospheric environmental problems. Among them, 28 in the steel industry, 16 in the coking industry, 203 in the cement industry, 34 in the glass industry, 174 in the building materials industry, 11 in the thermoelectric industry, 164 in the industrial coatings industry (including furniture). 63 in the metallurgical foundry industry, 24 containers in the graphics industry, 38 in the chemical and pharmaceutical industry and 300 in other industries.
In supervision and assistance, the typical problems encountered mainly include the following aspects:
First, the production suspension measures were not implemented in accordance with the provisions of the emergency plan for heavily polluted weather conditions. Companies such as Tangshan Quanfeng Sheet Co., Ltd., Binzhou Yangxin Hengli New Building Materials Factory, and Hebi City Fulai Ceramics Co., Ltd. were in normal production during the orange warning period, but did not implement the stipulated production stop measures. in the emergency plan. Among them, Tangshan Quanfeng Sheet Co., Ltd. was in normal production during the on-site inspection, and the shift record was “review”, suspected of false accounting.
Second, measures such as restriction of production and reduction of production were not implemented in accordance with the emergency response requirements due to highly polluted weather conditions. According to the relevant requirements, Hebei Tianzhu Iron and Steel Group Co., Ltd. and Hebei Xinwu’an Iron and Steel Group Xinhui Metallurgical Co., Ltd. had no more than 26 converters per day during the orange warning period, but The supervision and assistance working group related to the transfer of historical operations of the converter. The record found that the actual amount of extraction was around 45 kilns, which was much higher than the production restriction measures stipulated in the emergency response.
The third is the “first construction without approval” or the inability to obtain a contaminant discharge permit. Wuzhi County, Jiaozuo City, Houlin New Refractory Co., Ltd. did not obtain a permit to illegally discharge sewage, and its two furnaces under construction did not obtain an environmental impact assessment approval document. Langfang Chenjun Furniture Co., Ltd. and Cangzhou Hecheng Environmental Protection Equipment Co., Ltd. did not approve the first construction, and the companies were still in production during the emergency response to the heavy pollution climate.
Fourth, the pollution prevention facilities have not been installed or operated abnormally. During the production process of the drying oven in Shanxi Tongbang Technology Development Co., Ltd.’s third workshop, the supporting waste gas treatment facilities were not in normal operation, and the smoke from the workshop was discharged in a disorganized manner. A hollow gas collection pipe from Tianjin Shengshi Alliance Energy Saving Glass Technology Co., Ltd. production line is not connected and the fan is not connected to a power source Pollution control facilities do not work normally.
Fifth, there is an outdoor burning problem in some places. In Jiaozuo, Baoding, Tangshan, Dezhou, Jincheng, Puyang and other cities, there are cases of fallen leaves or garbage burning in the open air. Among them, the problem of open burning in Bo’ai County, Jiaozuo City, was more prominent, and 7 burning points were found in a short period of time.
In response to the clues of the problems found in the supervision and assistance, the Ministry of Ecology and Environment immediately assigned the relevant places to supervise and urge the actual implementation of the main responsibility of ecological environmental protection. Those who can initiate reforms must be rectified immediately; Those who violate the relevant laws and regulations must be investigated and dealt with strictly in accordance with the laws and regulations, and must be disclosed to the public. At the same time, we must draw conclusions from each other, conduct in-depth investigations and act with determination, do a good job with determination in reducing emergency emissions from a heavily polluted climate, crack down on all kinds of atmospheric environmental violations. and they continue to form a high pressure deterrent.
In the next step, the Ministry of Ecology and Environment will maintain the same direction and strength, continue to maintain a strict lead tone, focus on key areas, key time periods, key industries and key issues, and urge and guide governments. locals to adopt comprehensive measures to increase punishment. At the same time, we will further highlight the precision, science and law of pollution control, coordinate supervision and assistance, help localities find problems, promote problem solving, and transmit pressure effectively to ensure pollution control responsibilities are met.
(Source: Beijing Daily)
Massive information, accurate interpretation, all in the Sina Finance APP