What does the Ministry of Industry and Commerce say about the case of 600 electrical poles “fallen” in 30 minutes of rain and storm?



[ad_1]

Intellectual people

The electrical industry and EVN must review, evaluate, analyze and propose total solutions in the design, management, construction, supply of goods and operational management of this project.

The above information was answered by Mr. Do Thang Hai – Vice Minister of Industry and Commerce – at the regular government press conference this afternoon (October 2).

Before that, in the last 5 storms, up to 600 power poles were “down” in the central region, only in Thua Thien Hue there were 272 broken power poles. This is unprecedented in the last 10 years.

Mr. Do Thang Hai said that the Ministry of Industry and Commerce has led and mobilized the Central Power Corporation (EVNCPC) to overcome the damage from Typhoon No. 5 and in just 3 days, it has supplied enough electricity to the population.

Referring to the quality of the electric poles, Mr. Do Thang Hai said: The electric poles are part of the electric grid project, built by electric units on the basis of the provisions of the Construction Law and Decree 46. Issued by the government in 2015, specifying the responsibilities of investors, design consultants, and building units, including suppliers of building materials, structures, and equipment used on construction sites. .

What did the Ministry of Industry and Commerce say about the case in which 600 power poles were
Vice Minister of Industry and Commerce Do Thang Hai

According to Mr. Hai, the Ministry of Construction is in charge of state quality management of the project. On October 2, 2020, the Ministry of Construction issued a document on improving the quality of centrifugal reinforced concrete power poles used in overhead power transmission projects, requiring all units to carry out the related process using this type. of electric poles must be vigilant and have the measures to verify to better overcome the damage caused by storm No. 5.

On the side of the Ministry of Industry and Commerce, Mr. Hai said that this ministry, together with the owner of Vietnam Electricity (EVN), is the State Capital Management Committee in enterprises that apply to the electric industry and EVN to directly review, evaluate, analyze and propose total solutions in the design, management, construction, supply of goods and operations management.

The Ministry of Industry and Commerce also requested to coordinate with local authorities, ensuring the security corridor of the electrical network; strengthen the inspection of operations management, detect and manage critical points in the electrical network in a timely manner to guarantee network security.

The Ministry of Industry and Commerce also urgently requested the incorporation and incorporation of prevention, response and recovery from natural disasters in the development plans and strategies of the electricity industry and companies in the electricity industry.

What did the Ministry of Industry and Commerce say about the case in which 600 power poles were

Hundreds of electric poles were broken in storm No. 5 (photo: Ocean)

Previously, EVNCPC physically checked the areas where power poles were tilted, broken, and downed, and determined that the cause was due to falling green trees on the line, resulting in abnormal double impact force (both stormy wind and trees). lines) is too resistant to column structures, porcelain beams, conductors, etc., damaging the network infrastructure and broken columns.

“Some electric poles are located outside the residential area, in the corner positions, when there is a strong wind and the wind direction changes, turning and breaking the rope is also the cause of the collapse of the column” – said EVNCPC.

Explaining the quality of the electric poles, the EVNCPC representative reported that all the design, construction, materials and quality of the equipment were verified to ensure compliance with the regulations.

EVNCPC claimed that the acquisition of power poles was broadly tendered in accordance with the Law of Tenders from manufacturers such as 504 Consulting and Construction Co., Ltd., Construction Company Limited 384, Company Quang Nam Power Construction Joint-stock Company …

Chau Nhu Quynh