The Trung Luong – My Thuan Highway will temporarily allow the circulation of motorcycles and vehicles with less than 16 seats during the New Year’s peak days in Tan Suu 2021 – Photo: MATERIAL
On September 16, at the meeting with the contractors, Mr. Ho Minh Hoang, Chairman of the Board of Trung Luong – My Thuan BOT Joint Stock Company, the investor of the Trung Luong – My Thuan Highway project, stated that they plan ensure communication by the end of 2020 as promised to Prime Minister Nguyen Xuan Phuc in July 2020 and with voters across the country, especially more than 20 million people in the West, right after receiving the project. .
According to Hoang, although “opening the door” to pick up the car during the next Tet holiday is not part of a binding contract, but to solve traffic congestion on Highway 1 every Tet holiday, next time coordinated with the Functional forces from Cai Be, Cai Lay, Chau Thanh districts (Tien Giang province) to guide driving towards Trung Luong – My Thuan Highway to avoid traffic jams on Highway 1.
Mr. Ho Minh Hoang, Chairman of the Board of Trung Luong – My Thuan BOT Joint Stock Company, spoke about the plan to temporarily use the highway to resolve traffic jams on Highway 1 – Video: MATERIAL
“Before we are ready for motorcycles and vehicles with less than 16 seats to enter the Trung Luong – My Thuan Highway, we will invite journalists and functional forces to board 45-seat vehicles along the road for an inspection. evaluation, before putting them into temporary use, “said Mr. Hoang.
According to Hoang, the project has already completed about 65% of the workload., may “split fire” with Highway 1 through Tien Giang Province Tet is coming.
Workers are giving up constructive practices to put the highway into operation for the upcoming New Year 2021 – Photo: MATERIAL
However, Hoang said it is difficult to officially open this highway in 2021 if the authorities do not make a drastic decision to decide the location of the toll booth to pay for the project.
Mr. Nguyen Tan Dong, Managing Director of BOT Trung Luong – My Thuan Joint Stock Company, said that about 2 months ago, Prime Minister Nguyen Xuan Phuc instructed the authorities to quickly agree on the location of the toll. to accelerate the progress of the project, but so far, the Ministry of Transportation and the People’s Committee of Tien Giang Province have not agreed on the location of the station, which has caused difficulties for the plastic carpet and construction of the entire project.
Workers and engineers are issuing the construction practice to put the highway into operation on the occasion of the upcoming Tan Suu New Year 2021 – Photo: MATERIAL
Trung Luong – My Thuan Expressway Phase 1 under the BOT form with a total length of 51.1 km is a key road traffic project connecting the HCM City – Trung Luong highway. The project is implemented in BOT form, the total investment after adjustment is approximately more than 12.5 billion.