VND 4.3 billion canal route breaks in dry season due to complicated geology



[ad_1]

On December 30, the Ministry of Agriculture and Rural Development (Agriculture and Rural Development) issued a press release on the North Chu River – South Ma River (belonging to the Cua Dat Reservoir Project, Thanh Hoa Province) rupture. December 27.

The 4.3 billion VND canal route is broken in the dry season due to complicated geology - Photo 1.

The North Chu River – South Ma River suddenly broke on December 27

According to the announcement, immediately after receiving the information, on December 29, the mission of the Ministry of Agriculture and Rural Development, Thanh Hoa Provincial People’s Committee and experts verified and assessed the actual situation to clarify the cause. and direct corrective solutions promptly.

This announcement states that the Cua Dat Reservoir Project includes 2 work elements, including the focal dam and the main canal system. The main component of the works will be completed in November 2010 and the main component of the canal system will be fully completed in 2017. In which, the component of the canal system of the Norte Chu River – Río Sur Ma belongs to the project of the reservoir of What Dat, Thanh Hoa Province, is approved by the Ministry of Agriculture and Rural Development to invest in Decision No. 2542 / QD-BNN-XD of October 26, 2011.

The broken channel section is 70 m long (from position K5 + 170 to position K5 + 240) and belongs to the category of bridge across Song Am on the main channel of the North Chu River – South Ma River. Canal has been in operation since 2013 and officially delivered and put into operation in 2014.

For more than 6 years, the canal system from the north of the Chu River to the south of the Ma River has been in operation, ensuring adequate design capacity, promoting the efficiency of water supply for agricultural production, preventing droughts, people living without problems. . However, around 9:45 a.m. on December 27, at location K5 + 170 to K5 + 240, there was a landslide problem at the bottom of the canal, causing the canal to rupture.

As for the cause of the incident, according to the Ministry of Agriculture and Rural Development, the initial preliminary assessment shows that the canal is located in a complex geological structure, one side is a mountain, the other is a stream, excavated soil and fill. Heterogeneous; In particular, it is a section of floating embankment, high (about 6-7 m) high, located on a layer of eroded rock and with complicated sliding.

The 4.3 billion VND canal route is broken in the dry season due to complex geology - Photo 2.

Thanh Hoa province leaders went to verify the incident on December 29.

Currently, the Ministry of Agriculture and Rural Development is assigning the farm management unit to quickly overcome the problem, ensuring sufficient water supply conditions for the production of the spring crop in 2021 in the correct season. At the same time, it is necessary to quickly coordinate with local authorities to review, assess and compensate those affected by the incident.

At the same time, the management and operation units are required to re-evaluate the entire route of the main canal, as well as the main works, to timely detect possible problems, avoid similar incidents. .

Previously, around 9:45 am on December 27, the North Chu River – the section of the South Ma River that passed through the Minh Loi village (Phung Minh commune, Ngoc Lac district) suddenly broke and sank about 1.5. -2 m. Before the above incident, the Irrigation Construction Investment Management Board 3 informed the local authorities, at the same time mobilized forces to install fences, put up warning signs so that people know how to avoid.

North Chu River – The South Ma River has a total length of more than 370 km, a total investment capital of more than 4.3 billion VND. Construction began in 2014 and went online in 2016, supplying water to more than 31,000 hectares of agricultural land.