Thua Thien Hue took the police to the Thuong Nhat hydroelectric power station to monitor the water discharge 24/24 - Photo 1.

Thuong Nhat Hydroelectric Plant is required to open all 5 water outlets to deal with Typhoon No. 13 – Photo: VAN DUNG

On the morning of November 14, news from the People’s Committee of Thua Thien Hue province said that the police force had been dispatched to the Thuong Nhat hydroelectric area to monitor all the water discharge into the downstream reservoir, preventing this hydroelectric accumulate excess water. permitted.

Previously, Thuong Nhat Hydroelectric Power had illegally stored water and did not obey the Thua Thien Hue Province People’s Committee’s response to Storm No. 13. The functional forces of Thuong Nhat commune measured the water level in the reservoir on the morning of November 13 at an altitude of 115 m.

The Thua Thien Hue Provincial People’s Committee has issued an emergency power specifically for this hydroelectric to request Central Vietnam Hydropower Investment Joint Stock Company (owner of Thuong Nhat Hydropower) to operate and open 5 valve gates of the plant to ensure that safety dams and downstream.

The Thua Thien Hue Provincial Police ordered the Nam Dong District Police and the Thuong Nhat Commune Police to monitor the water discharge operations 24 hours a day, 24 hours a day. The investor of Thuong Nhat Hydroelectric Power Plant is required to have a plan to ensure the safety of lives and assets at the power plant.

At the same time, the Central Energy Corporation is requested to stop buying electricity from this plant until the hydroelectric plant fully complies with the regulations on safety management of dams and lakes.