[ad_1]
The 18th floor of the 8B Le Truc building is perforated but still preserves the system of beams, columns, lifting boxes to guarantee the safety of the building – Photo: XT
The violation of the building on floors, exceeding the height of the building permit issued in the 8B Le Truc high-rise project took place in 2012, after 9 years of handling violations, so far, the city of Hanoi has basically handled finished the errors in the project.
According to the People’s Committee of the City of Hanoi, the cause of the errors in the construction of the 8B Le Truc high-rise project is mainly due to the lax management of the authorities and local government, there are errors in the licensing process. judgment.
Project investor: Le Truc Garment Joint Stock Company violates the law, does not coordinate with local authorities.
Compared to the building permit granted, the 8B Le Truc construction project exceeded 1 floor; 15.89 m above the allowed height; wrong about setback space, building level setback, leading to increase in build floor area above 6,900m2.
The 8B Le Truc high-rise building error handling also faces many problems in demolition of the wrong construction area and height.
The handling of project violations is divided into 2 phases, phase 1 (2016) The Ba Dinh District People’s Committee removed the staircase and the 19th floor of the building; Phase 2 (2020) continues to dismantle the 18th floor.
So far, the Ba Dinh District People’s Committee has dismantled all the building walls, partitions, doors and equipment on the 18th floor, completing the cutting volume of 1,268 m.2 18th floor of the building.
According to the Hanoi Institute of Construction Science, Technology and Economics, the structure of the 8B Le Truc building after demolition is still safe, whether there is deflection and the size of the cracks in the structures observed. exceeded the allowed threshold.
Building 8B Le Truc after cutting the roofs – Photo: NT
Currently, the house at 8B Le Truc has 17 floors and attic, the height to the ceiling of the 17th floor is 58.5 m, the height of the building compared to the building license still exceeds 5.5 m, the surface increases by about 2,800 m.2.
Following the direction of the Standing Committee of the Hanoi Party Committee, the Hanoi People’s Committee has issued a document that allows the retention of the column structure, beams, central structure and suspended beams on the 18th floor; beams, columns, walls that will be integrated into stairs to ensure safety during the operation of the building.
In the coming time, the departments, branches and the Ba Dinh District People’s Committee will continue to closely monitor the 8B Le Truc building and guide the investor to strictly comply with financial obligations to the State, including the return of the budget. Financing for the execution, urgent completion of works according to architectural plans, technical design documents approved according to regulations, guaranteeing the safety of 8B Le Truc’s and surrounding works, guaranteeing aesthetics. , Urban architecture.
The permission to retain some of the above items, according to the city of Hanoi, is due to technical requirements, which ensure the structure and safety of the building by the suspension beam, the retaining column partially supports the lifting force of the floors . Then if the leak can affect the overall structure, it will affect the safety of the building.
These items will be revamped to become flower frames, raised pots, not to be used for other purposes.