The city announced “the full handling of the violations at 8B Le Truc in accordance with the Prime Minister’s instructions”, on the night of November 7.
“The city has strictly implemented the direction and management according to what is established by law, guaranteeing the absolute safety of the works and the interests of the related parties,” the municipal report said.
The current state of the work after the execution is still 17 floors and the staircase, the height to the ceiling of the 17th floor is 58.5 m, compared to the building permit which exceeds the height of 5.5 m; the constructed area increased by 2,800 m2.
Hanoi allows the 18-story suspended column, beam, stair core and beam structure to be retained for the reason “to ensure the structure and safety of the building: due to the suspension beam, the retaining column partially supports lifting force “. for the ground floor. “If the breakdown continues, it can affect the overall structure of the building. These elements are completed in flower trellises, flower pots and are not used for other purposes.
During the last 5 years, the violations and the delay in handling the violations in the 8B Le Truc project have been repeatedly mentioned in the voter meetings, in the National Assembly forum. The Prime Minister has repeatedly requested in writing that the violations in the project be fully handled.
The demolition of the offending party in the 8B Le Truc project is divided into two phases. Phase 1 as of November 2015 and completed after approximately one year with the dismantling of the staircase and 19th floor. Phase 2, beginning in May 2020, dismantling of all masonry walls, partitions, doors and floor; Full volume of floor cut 18 with area.
The Hanoi People’s Committee assigned relevant units to continue to closely monitor the project, instructing the investor to strictly comply with financial obligations to the state (including the return of the budget for its execution) … Phase one (breaking the turn and the 19th floor), the budget is temporarily estimated at 14 billion VND. The total estimated cost for the execution of phase 2 (demolition of the 18th floor) is VND 38.2 billion. In which, the budget to implement the execution plan is 10 billion VND; Advance funding for the manipulation, dismantling and dismantling of the 18th floor amounts to 28.2 billion VND.
On the morning of November 8, Ms. Duong Thi Thu Nga, owner of an apartment on the 18th floor, said that when the authorities forced the 18th floor, her family filed a lawsuit against the Ba Dinh District People’s Committee before the Hanoi court.
“Yesterday, the court called my family to present some documents, take testimony,” said Ms. Nga and explained the reason for the lawsuit because when the family bought it, the project had a building permit on floors 17 and 18 His family received the crude delivery and completed the interior, moved the furniture, there was an inspection and then the duress.
“The application in the sixth year, we were too tired and we wanted to return an apartment in the family project that had mobilized all the financing and also borrowed to buy,” said Nga.
Mr. Pham Quang Lung, who bought a house on the 16th floor, said that the application has been completed, the residents will work with the investor to discuss the repair and completion to bring the building into operation soon. “We have been waiting for 5-6 years, so we look forward to moving into our new apartment this Tet vacation,” he said.
The investor in the project is Le Truc Garment Joint Stock Company.
According to the results of the interdisciplinary inspection in Hanoi, the 8B Le Truc project has many errors compared to the granted building permit. From the 8th floor (on the extended Tran Phu street), there must be a setback space of a 3.36m high block of flats compared to the base block, but the investor has built it straight up to the ceiling.
The gable in the east is designed from a height of 44 m to 15 m and at a height of 50 m, the step is added 5.3 m to the west, but the owner does not build Increase the construction floor area.
The work is 53m high to the top of the ladder if the permit is done correctly. In fact, the investor arbitrarily increased the height of the floors, built the 19th floor, the total height is about 69 m (more than 16 m, equivalent to 5 floors). The constructed area under the building permit is almost 30,000 m2, but the investor has built around 36,000 m2, an increase of more than 6,000 m2 compared to the license.
Vo hai