Discharge from a flood of hydroelectric power made people lose nothing: Compensation – DVO



[ad_1]

Dak Mi Hydropower Joint Stock Company (the investor of the Dak Mi 4 hydroelectric project) issued an announcement at 15:00 on October 28 about the operation of the Dak Mi 4 hydroelectric reservoir (increasing the discharge flow by 2 times). According to the announcement of this company, the start of the flood discharge is at 3:30 p.m. on the same day, the overflow discharge is expected to reach 11,400 m3 / second. The discharge from the Dak Mi 4 hydroelectric power that is discharged downstream is 5,100 m3 / s. The sudden and too large discharge from the flood combined with heavy rains caused the commune of Ca Dy and Thanh My city to suffer severe damage. Mr. A Viet Son, Vice President of Nam Giang (Quang Nam) District said that the investor should compensate people for the damages.

Always be careful with makeup
Many households lost their money after historic floods. Photo: Phunuonline

Sharing and fully supporting the request of Nam Giang district leaders, LS Truong Xuan Tam said the hydroelectric power plant announced the flood discharge to the people 30 minutes before the plan, with the discharge is too large, people are avoiding the storms. unable to rush home in time to move things to safety and cause serious harm to people is wrong hydropower.

Mr. Tam said that the damage to people and property of both people and localities due to hydroelectric power from the floods is very clear, so the local government should ask the authorities to intervene to clarify the behavior. rape; The local population synthesizes the loss of property, including the local infrastructure to initiate a lawsuit, requests the investor for compensation, including the request for prosecution, criminal handling in accordance with in accordance with the law.

When there are enough reasons, the basis claims that the investor has made a mistake, the wrong process causes harm to the people, the government will support and guide the people to complete the lawsuit procedures, each citizen will be subject to suing the investor. With the infrastructure works in the area under the management of the local government, the local government can be the representative subject to demand.

On the basis of requiring the investor to operate the hydroelectric compensation, it is also very clear, specifically, the LS said that there are 3 causes: First, having illegal acts; Second, there is damage to occur; Third, there is a causal relationship between the illegal act and the consequences.

“Thus, here people are victims of investors who operate the hydroelectric plant that discharges floods too suddenly, unexpectedly, in the context of passive people, incapable of responding quickly, causing great damage. about people and property is wrong.

Therefore, the compensation for damages is very fair and clear, the hydroelectric construction investor is not a philanthropist, it is not a charitable agency that distributes relief items, so people do not need to ask for support from hydroelectricity in this case but requires the investor to be responsible and compensate ”, emphasized the LS.

Mr. Tam also pointed out that damage statistics should be very specific and should be converted into money in detail, eg how much money is damage to livestock, how much houses, crops, assets. How much … must be very specific, detailed. Verification of damage at this time according to Mr. Tam is difficult, however, in the context of floods, the addition of large hydroelectric discharges causes houses and properties to be washed away, people lose the referendum. The surrounding evidence is the evidence showing the consequences of misconduct due to too large flood discharge hydroelectric power, flood discharge time too fast, authorities and people cannot back down.

Speaking more about flood discharge hydroelectricity, Mr. Truong Xuan Tam said that flood discharge hydroelectricity to ensure the safety of the dam lake is necessary, however, flood discharge causes harm to people downstream , which generates public opinion. Failed associations also occurred and existed for many years. This shows that the initiative of the investor in the operation of hydroelectricity is not high enough, not being able to give warnings and forecasts on the amount of stored water, the storage time and the discharge time, which leads to the accumulation of water. . water before the flood season, when the floods return, not in time, they need to be discharged suddenly, discharged at night, discharge a large amount of water, and cause great harm to people.

This has been repeated too many times, therefore Mr. Tam said that proper lessons need to be taken for irresponsible and indifferent hydro operators, leading to wrong things. According to Mr. Tam, handling must also be strictly followed by law, including liability for compensation and criminal liability if necessary.