The investigation agency of the Ministry of Public Security processed 13 more suspects to clarify the irregularities that occurred on the Da Nang – Quang Ngai highway.

On the afternoon of 7.12, the Ministry of Public Security said that the investigating agency had prosecuted 13 more suspects to clarify the role related to the case that occurred in the Vietnam Expressway Development Investment Corporation (VEC), the Project Management Board. . Highway Da Nang – Quang Ngai and some drives.

Eight of the 13 defendants have just been indicted for crimes committed on the Da Nang - Quang Ngai highway project.
Eight of the 13 defendants have just been indicted for the crimes committed at the Da Nang – Quang Ngai highway project.

The defendants have just been prosecuted for “violating the regulations on investment in construction works, causing serious consequences”, according to article 224 of the Penal Code.

Previously, the investigating agency prosecuted a total of 19 defendants in the VEC, the project management board and the construction contractors for “Violation of the regulations on investment in construction, causing serious consequences.”

VEC is the investor in the Danang – Quang Ngai highway project. The route has a total length of 139.2 km with an approved cost of more than 34,500 billion VND and divided into 2 phases.

The investigating agency determined that when implementing the project, the VEC and the construction contractor, the supervisory consultant, and related units did not meet technical standards, resulting in poor quality, causing damage. when operating and exploding.

According to the inspection results, 7/7 packages of phase 1 of the foundation layers, foundations and pavement do not meet technical standards. This is the cause of the damage to the building.

The Ministry of Public Security also determined that in monitoring activities, VEC hired many units abroad to carry out this task. However, in reality, on-site construction supervision has only a few foreign engineers, mainly Vietnamese engineers with little experience and ability.

To occur the above violations, the Ministry of Public Security evaluates the cause because the investor, the contractor and the related unit have relaxed the management and supervision; Unclear regulations outlined, lack of accountability at each stage of the project.