The industrial slaughter plant project of a Ha company is in danger of bankruptcy due to proceedings – Photo: TRAN MANH
Ms Nguyen Thi Hong Tham, Director of An Ha Co., Ltd. spoke urgently at the meeting with the Ho Chi Minh City Department of Agriculture and Rural Development about the progress of the industrial livestock slaughter plant and poultry in the city on the 18th. -11.
Ms. Tham said that the Xuyen A (Cu Chi, Ho Chi Minh City) cattle slaughter plant project was implemented by An Ha Company in the past 5 years in accordance with the City People’s Committee’s investment solicitation policy. Ho Chi Minh. But because there is only one ditch within the project with an area of less than 390m22 in total almost 30,000 m2 (3ha) but from 2018 to mid-2020 the company cannot receive the decision to deliver the land for construction.
After many requests for help, on September 14, 2020, the Ho Chi Minh City Department of Natural Resources and Environment (Department of Natural Resources and Environment) issued a document No. 8185 / STNMT-QLĐ to submit to the People’s Committee of Ho Chi Minh City for their consideration and decision to lease the land to the company. to build a livestock slaughter and food processing factory in An Ha.
However, the Department of Natural Resources and Environment introduced the content “form of land use: land lease with annual rent payment”. On October 14, 2020, the Ho Chi Minh City People’s Committee issued Decision No. 3845 / QD-UBND for the company to lease land with the land use form that pays annual land rent.
Hundreds of billions of VND spent by An Ha Company to import machinery from 2018 to keep dust in warehouse – Photo: TRAN MANH
According to Ms. Tham, this decision is like a “final blow” for An Ha Company. Because if the annual rent for the land is paid, the company cannot take the project to mortgage the bank to obtain capital to build and complete the factory. While engaged in infrastructure and machinery importation, An Ha has spent more than 100 billion VND since 2018.
An Ha Company consecutively sent letters to the Department of Natural Resources and Environment and the People’s Committee of Ho Chi Minh City requesting to adjust the form of land use, which is to rent the land with a one-time rental payment for the entire period. lease.
However, the Popular Committee of the City transferred the request to the Department of Natural Resources and Environment. Ms. Tham also met many times with DONRE to point out the provisions of the land law that allow the company’s project to lease land with one-time payment, but the representative of DONRE said that “the law says so but the Popular Committee of The City. HCM has a different rule “so this department cannot propose a lump sum payment.
“We are exhausted because every month we pay billions of dong from 2018 until now. If we can’t mortgage the project to borrow capital to complete the plant and get it up and running, we are forced to go bankrupt. Praying that it is so difficult to comply with the law, “said Ms. Tham.
In response to Ms. Tham’s opinion, Mr. Dinh Minh Hiep, Director of the Department of Agriculture and Rural Development, asked the representative of the Department of Natural Resources and Environment to respond.
However, the representative said that it was only the replacement, without having authority to decide. And upon hearing Ms. Tham’s reflection, this representative called the department and received information that DONRE will have a meeting on this topic.