On the night of October 9, the Investigative Police Agency (Ministry of Public Security) said that it had issued a decision to prosecute the accused, had executed an order to search and detain Mr. Nguyen Manh Hung, deputy director general of Investment Corporation. Vietnam Highway Development (VEC) – Investigate the crime of “Violation of the regulations on investment in construction works, causing serious consequences” of article 224 of the Penal Code of 2015.
Regarding the case, the investigative agency of the Ministry of Public Security also processed and ordered the arrest and prohibition of leaving the residence with 6 other defendants from the VEC Corporation and the Da Nang Highway Project Management Board. – Quang Ngai. about the same crime.
The previous decision has been approved by the People’s Prosecutor of the same level.
These 7 suspects were accused of violating construction regulations during commissioning and construction of the Danang – Quang Ngai Highway.
Previously, on November 14, 2019, the police investigation agency (Ministry of Public Security) indicted the accused with Nguyen Tien Thanh, former director of the Da Nang – Quang Ngai Highway Project Management Board; Ha Van Binh, Former Director of Package 7, Da Nang – Quang Ngai Highway Project Management Board; Pham Dinh Phu, Deputy Managing Director of Phuong Thanh Company, Director of the Executive Board of Package 5 and Nguyen Thanh An, Member of Cienco 1, Deputy Director of the Executive Board of Tender Package No.7.
Up to this point, in relation to the previous case, The investigating police agency (Ministry of Public Security) processed the accused with about 20 people.
Previously, since the end of October 2018, the Board of Members of VEC Corporation reviewed the General Director of VEC on the responsibility of direct responsibility and management of the operation and maintenance of the project, but did not seriously implement the resolution of the Council of Partners , for consequences to occur.
According to the VEC representative, after more than a year of operating 65km of highway, some local damage appeared. Inspection units have reported, but the contractor did not repair in time, thoroughly, causing further damage.
Along the route, 21 locations out of a total of 426 bridges and culverts were leaked and leaking. In some positions, the slope slides because the layer of grass that protects the slope has not developed in time …
The Danang-Quang Ngai highway project is invested by VEC Corporation under the State Capital Management Committee in the company. The project has a total length of 139.2km, construction began on May 19, 2013.
After completing the elements of the main route, the State Board of Acceptance and Acceptance has verified, evaluated and approved the commissioning and commissioning in accordance with the regulations. In particular, the Da Nang – Tam Ky section was put into operation from August 2, 2017, the Tam Ky – Quang Ngai section will open the car and be put into operation from September 2, 2018.
After 14 months of commissioning, on the Da Nang – Tam Ky section, there was partial damage to the road surface with the damaged area (potholes in the rough asphalt layer) of about 70 m.two out of a total of 3.1 million mtwo road surface.
Some bridges and underground tunnels for people who live along the entire route appear to have leaks and leaks; Some locations on the slope eroded because the contractor did not complete the turf and reinforcement planting.