Eliminate the risk of dissolution of the construction site of the Thu Thiem 2 bridge | Urban



[ad_1]

Representatives from the Ho Chi Minh City Department of Transportation said that from April 2-4, the District 1 People’s Committee handed over the facilities to build the Thu Thiem 2 Bridge to the investor.

The Transportation Department added that at the meeting between the Department, the District 1 People’s Committee and the investor, the parties agreed to wait for the Thu Thiem 2 bridge to be rebuilt before April 15.

In particular, the Popular Committee of District 1 cleared the land urgently to ensure progress, as well as the investor commits before April 30, 2022 that the construction will be completed.

Earlier, Dai Quang Minh Real Estate Investment Joint Stock Company, the investor of the Thu Thiem 2 bridge project, said that in recent years, the project had to be built sparingly and stopped construction from September to 2020.

The reason is that the project has not solved the problems related to legal procedures, the payment of BT contracts and the clean-up of the site.

Meanwhile, the consortium of contractors suggested that by April 15, if construction is not resumed, the site will be disbanded.

In particular, the specialized equipment for construction, which is the lifting platform, will be transferred to the construction site in Singapore, while the cable-stayed equipment will be transferred to South Africa …

For this reason, the investor proposes to the Popular Committee of the City that it soon have solutions to face the difficulties in the legal procedures. Specifically, pay BT’s contract and complete site cleanup to continue construction of the items required by the contractor, such as the bridge tower, install the girders to S1, and stretch the remaining flanges.

Tangled 13,000 mtwo land

The Thu Thiem 2 bridge project started in 2015 and is expected to be completed in April 2018. The Thu Thiem 2 bridge connects the Thu Thiem urban area with the center of District 1.

The bridge has a total length of 1,465 m, of which the bridge section is 885.7 m long with six lanes, with a total investment of VND 4,260 million.

The project is 70% complete, but is due to be suspended as of September 2020 due to issues with cleanup compensation in District 1 with a total area of ​​approximately 13,000 m2.two.

The risk of dissolving the construction site of the Thu Thiem 2 bridge

The risk of dissolving the construction site of the Thu Thiem 2 bridge

(PLO) – The consortium of contractors for the Thu Thiem 2 Bridge project proposes to the investor that until April 15, if the work is not rebuilt, the construction site will be dissolved.