Cancellation of the project ‘hanging’, the interests of the people are still suspended | News



[ad_1]

However, the elimination of “hanging” is done dripping, they are not rare cases of planning from the planning stack, overlapping projects cause frustration.

The Ho Chi Minh City People’s Council meeting in late 2020 issued a resolution to cancel 61 projects (DA) in the city due to slow implementation. However, there, as pointed out Youth, there are some projects that immediately restore people’s rights to land, but there are also projects that “hang” will continue the new project husband …

Paying benefits to people

Located next to the 23.9 park (District 1), the project “golden triangle” Pham Ngu Lao – Tran Hung Dao – Nguyen Thai Hoc (P. Pham Ngu Lao) although has selected an investor in the form of land allocation in 2008, but then the results were canceled by order of the Prime Minister.

For 2016, the project was included in District 1’s 2016 land use plan, then assigned to the Planning and Investment Department to prepare the bidding procedures for the project, with a construction investment cost of more than 7,600 million VND. At the end of 2018, the Department of Natural Resources and Environment placed this project on the undelivered list after 3 years and presented it to the Ho Chi Minh City People’s Committee to take out the land use plan.

However, it took almost 2 years for this project to be officially canceled with a resolution of the Ho Chi Minh City People’s Council. For the past 12 years, the people on this project have been miserable because they cannot build spacious houses like other areas. Regarding this matter, Mr. Nguyen Van Dung, Chairman of the People’s Committee of District 1, the information about the Pham Ngu Lao – Tran Hung Dao – Nguyen Thai Hoc “golden triangle” area project has been canceled by the Council. Popular of Ho Chi Minh City. The land is restored as before, people can build and renovate their houses.

Of the 10 projects on the rice land use change list, which have been “suspended” in this phase, 4 projects are located in District 9. Specifically, the project in the residential area of ​​Long Phuoc Garden ( P. Long Phuoc) was canceled because there was an invading home waiting to resolve the dispute. Another 3 projects were canceled for the same reason, which “does not have investment approval in accordance with the Investment Law (modified) and the investor does not register the demand for land use”, among them: Sanctuary Villas Cove (Phu Huu neighborhood ), My Thinh Phu apartment complex (Phu Huu and Phuoc Long B neighborhood), Cienco 585 apartment building (Truong Thanh neighborhood).

Mr. Tran Van Bay, Chairman of the People’s Committee of District 9, informed that after having the resolution of the People’s Council of Ho Chi Minh City, the departments, depending on their authority, will advise the People’s Committee of Ho Chi Minh City to take the following measures to guarantee rights. benefit people. Regarding the next specific management direction, Mr. Bay said that he will publicly announce the canceled projects to the people and at the same time, the District 9 Urban Management Department will review the projects and consult with the community. Inform the Planning Department and KT about the planning of the projects for their adaptation or cancellation. After it is approved, based on the new planning, the district will guide people to use the land in accordance with the approved plan. If it is residential land, the district will guide people to move to residential land.

In District 8, for the urban beautification project, Rach U Cay (in 3 districts: 9, 10 and 11) has been “suspended” since 2010 and the “suspension” has been removed at this stage, Mr. Pham Quang Tu , Vice Chairperson of the District 8 People’s Committee, said he is considering adjusting the planning of this area to ensure the interests of the people within the project area.

Project husband project, people’s interests are still “hanging”

In the list of projects canceled due to slow implementation, there are also a number of major traffic projects, which solve traffic jams in Ho Chi Minh City, such as the expansion and improvement of Nguyen Kiem Street (from the street Nguyen Thai Son to intersection 6 Go Vap, Go Vap district); to upgrade and expand NH13 (the section from the Binh Phuoc intersection to the Binh Trieu bridge, Thu Duc district); upgrade and expand a series of roads and alleys in District 6, District 7, Thu Duc District, Cu Chi District …

In particular, the NH13 upgrade and expansion project, which is about 4.6 km long, located at the northeast gate of Ho Chi Minh City, connecting with Binh Duong and Binh Phuoc, has been “on hold” for almost 20 years. After many times of scaling the road surface, the project was still stalled and finally “dead”. The irony is that even though this project was canceled, the rights of people on this road have not been restored, but are still restricted by another project.

According to the transportation infrastructure development project in the Ho Chi Minh City area in the period 2020 – 2030, which is planned by the Department of Transportation, the NH13 expansion project is one of the national highways, connecting the region in urgent need of investment. to solve traffic congestion … NH13 is expected to be expanded to 53-60m, the total investment is about 9.992 billion VND from the budget, of which construction costs are only 1.38 billion VND , The rest are dispatch expenses and other expenses.

Mr. Tran Chi Trung, Head of the Planning and Investment Department (Department of Transportation), explained that the NH13 expansion project was previously planned to invest in the form of a public-private partnership, but due to the expiration of the implementation time, no has been implemented. to withdraw the project. The Department of Transportation has informed the Ho Chi Minh City People’s Committee about the policy of converting this project into investment in the form of public investment. Mr. Trung stated that the cancellation of this project does not mean that people build on the edge of the land near NH13, but that they must also follow the planning.

You must listen to people in planning

Reply Youth Regarding project cancellation, will planning be canceled? Mr. Nguyen Thanh Nha, Director of the Department of Planning and Economic Affairs, said: “In urban development, planning must and cannot be canceled, if not feasible, adjust.” According to Mr. Nha, the cancellation of projects that are slow to be implemented by the Department of Natural Resources and Environment advises the Ho Chi Minh City People’s Committee or the Ho Chi Minh City People’s Council to cancel, the Planning Department- KT just reviews the plans. Mr. Nha stated that the planning review was done by districts and districts; If planning is deemed inappropriate, localities report it, the Planning Department and KT coordinate with other departments to review and propose to adjust the plan accordingly and feasibly.

“No one is responsible is silly”

Dr. Tran Quang Thang, Director of the Ho Chi Minh City Institute of Economic Management, acknowledged projects that have not been implemented after 3 years, showing that planning and investment calls are “out of date” in terms of scale and stature. The project was canceled due to impossibility of execution, which shows that the plan has not been fulfilled. However, it is worth mentioning that many projects were canceled, but the planning remained the same, thus keeping people’s interests restricted.

“When planning no longer makes sense, it loses its value in itself. Therefore, it is necessary to have an immediate solution, such as switching to a new plan or eliminating it to restore the interests of the people, “suggested Dr. Thang, adding:” For a long time, people have not been consulted on how to do That planning must be done methodically in the coming time, to consult with people about the planning work ”.

According to Dr. Thang, it is not reasonable that the schemes are “generating” and restricting people’s rights to housing and land, but “no one is responsible”. Therefore, when making a plan, specific criteria must be given to determine who owns the responsibilities, due to unfeasible planning by public officials or low-skilled investors.

At the scientific seminar “Potential for urban development in District 3” that took place yesterday (December 22), Mr. Vo Van Hoan, Vice Chairman of the People’s Committee of Ho Chi Minh City, acknowledged the formulation, evaluation and approval of the regulation La Planning is a complicated process, it takes time, so you need close coordination to accelerate progress, create good planning products to attract people and companies to participate, create resources. Develop. If the three benefits cannot be harmonized: the state, the people and the investor do not receive the consent of the people, they inhibit investors, the planning project becomes unviable and leads to “suspended planning”. “.

Therefore, the adjustment of the next urban construction planning in Ho Chi Minh City not only follows and promotes the advantages of natural conditions, but must understand the legitimate needs of the people who will be affected by the planning. . “You really have to seek, listen to the opinions of people in the process of preparing, evaluating and approving the planning project. Create conditions for people and companies to participate in the implementation of the plan, comply with and voluntarily supervise the implementation of the plan. In particular, the government must quickly adjust and supplement policies to guarantee the rights and interests of residential communities and businesses, ”said Mr. Hoan.