Thai Nguyen Iron and Steel Case: Unable to price equipment provided by Chinese contractors | News



[ad_1]

Regarding the illicit case that occurred in phase 2 of the production expansion project of the Thai Nguyen Iron and Steel Corporation (TISCO), according to the conclusion of the Investigative Police Agency of the Ministry of Public Security, June 2019 East The cargo has written to the Property Valuation Council of the Thai Nguyen Province People’s Committee to evaluate the ownership of 42 cars of all types and 5 diesel locomotives of all types.

The Thai Nguyen Provincial People’s Committee has established an assessment council in criminal proceedings. However, after 6 months of conducting the appraisal, the Thai Nguyen Province Property Appraisal Council issued a written denial of appraisal, due to insufficient reasons, rationale, information and conditions to perform the appraisal.

In December 2019, the Investigative Police Agency of the Ministry of Public Security continued to send a written request to the Ministry of Transportation to establish the aforementioned Asset Valuation Council. Four months later, the Ministry of Transport established the Property Valuation Council as appropriate. However, at the end of June 2020, the Ministry of Transportation issued a document stating that there was not enough information and grounds to carry out the appraisal, and said that “the request of the Investigative Police of the Ministry of Security was exceeded Public “. by professional knowledge of the members of the Assessment Council of the Ministry of Transport ”.

According to the investigation conclusion, during the execution of the second phase production expansion project, TISCO signed an EPC package contract with the Chinese contractor China Metalurgical Science, Technology and Trade Corporation (MCC). ). Although the project is in progress, MCC has halted construction, delaying the project for more than 10 years, but TISCO has paid the contractor more than $ 107 million, equivalent to VND 2,064 million.

MCC has imported and supplied around 3,500 tons of equipment and machinery to the site, but identified many series of equipment that are not according to specifications, with differences in origin, supplier name, origin, information. Technical data… The long delay of the project has caused a loss of more than 830 billion VND for this project, which is interest on bank loans.

The Government Inspector’s conclusion on this project also previously indicated that MCC provided 42 cars worth more than $ 1 million without import taxes, but all of these vehicles had differences in discharge rates. between the documents that TISCO requests for registration and the results of the inspection of the Registration Department. Of these, there are 29 dump trucks capable of hauling 16 tons / vehicle. However, each of the test results contained only about 9.4 tons.

MCC also delivered 5 locomotives worth $ 5.4 million that did not meet specifications, suppliers under signed contracts … In total, MCC delivered machinery and equipment with differences in export. Origin, specifications, inconsistent with Vietnamese regulations are worth up to 38.8 million dollars. Currently, some equipment provided has been rusted, damaged, severely affecting the quality and progress of the project.