Watch the train on the Cat Linh – Ha Dong railway in the first morning to test the whole route from Fly cam



[ad_1]

Looking at the train for the first time, try the entire route on the Cat Linh - Ha Dong Railway - Photo 1.

At 5:00 am on December 12, the Cat Linh – Ha Dong urban rail project commissioned the entire system in 20 days – Photo: PHAM TUAN

Consequently, cThe train will run continuously from 5:00 am to 11:00 pm (from December 31) on the 13 km long Cat Linh – Ha Dong route. At each station, the train will stop for about 30 seconds to pick up and drop off passengers, just like when running a commercial. Trains run 6-7 minutes / trip, peak hours can be 2-3 minutes / trip. Every day there will be between 6 and 9 trains in operation.

During the 20-day trial, all stations had Vietnamese personnel on duty in the control room, ticket office, and platform; electronic boards, active speakers to guide train passengers.

More than 600 employees will be divided into 2 work shifts, operating the elements in the station and the operations, maintenance and repair center, as commercial operations.

In addition, about 200 Chinese experts from the China General Contractor and the project team contractors are also present on the route to be monitored.

See the train for the first time to test the whole route on the Cat Linh - Ha Dong Railway - Photo 2.

The train passes through Hoang Cau Street seen from above – Photo: PHẠM TUAN

The Railway Project Management Board (Ministry of Transport) said that the test execution phase will verify the safety of the system and the operational capacity of all employees. This is a required step in the security assessment process performed by the ACT consultant (independent system security assessment consultant).

Based on the results of the trial operation, in the first quarter of 2021, a consortium of independent consultants is expected to issue a system security certificate for the project. After that, the Ministry of Transport (investor) will take over the project and hand it over to Hanoi for management and operation.

The first images of the Cat Linh – Ha Dong train travel the entire route between 12 and 12 in the morning:

See the train for the first time to test the whole route on the Cat Linh - Ha Dong railway - Photo 3.

The trains run continuously in both directions from 5 am to 23 pm for 20 days to verify and evaluate the entire system – Photo: PHAM TUAN

See the train for the first time to test the whole route on the Cat Linh - Ha Dong Railway - Photo 4.

Trains run 6 to 7 minutes per trip, peak hours can be 2 to 3 minutes per trip. Every day there will be 6-9 trains in operation – Photo: PHAM TUAN

See the train for the first time to test the whole route on the Cat Linh - Ha Dong Railway - Photo 5.

The “team” section of the train in the fog, running ice on the Cat Linh – Ha Dong railway is more than 13 km long – Photo: PHẠM TUAN

Seeing the train for the first time to test the entire route on the Cat Linh - Ha Dong railway - Photo 6.

The Cat Linh – Ha Dong railway project was approved for investment in 2008 with an implementation period of 5 years, from November 2008 to November 2013 – Photo: PHẠM TUAN

See the train for the first time to test the whole route on the Cat Linh - Ha Dong Railway - Photo 7.

The train slowly enters Thuong Dinh Station (section in Nguyen Trai -Thanh Xuan Street) – Photo: PHẠM TUAN

See the train for the first time to test the whole route on the Cat Linh - Ha Dong Railway - Photo 8.

The train turns the corner beautifully when viewed from the flycam – Photo: PHẠM TUAN

Video: See the panoramic view of the train running along the Cat Linh – Ha Dong Railway