On November 7, the Gia Lai province police said they had prosecuted the case of “Violation of building regulations causing serious consequences” that occurred on the Ho Chi Minh road project bypassing the district section by Chu Se. .

The road to avoid passing through the city of Chu Se was crushed

The Ho Chi Minh highway project has an investment of nearly VND 250 billion by Project Management Board 6 (PMU 6, Ministry of Transport) as an investor. The road is 10.8 km long, designed according to the grade 3 flat scale.

In September 2019, when it was just completed, the road built by 471 Joint Stock Company (Nghe An) suddenly sank about 150 meters.

The prosecution of the 250 billion dong highway case just ended shattered in Gia Lai - Photo 2.

After obtaining the results of the inspection, the police agency processed the case

The reason determined by the Ministry of Transportation is that there are two layers of soft soil under the hard crust, widely distributed in the incident area and groundwater is produced. However, in implementing the project, this phenomenon has not been found to be fully addressed.

“The design consultant has not discovered and has not proposed an additional survey when the section of the route passes through areas with special and unfavorable topographic, geological and hydrological conditions” – concludes the Ministry of Transport. Later, when the construction unit was organizing the repair, the Gia Lai province police requested a pause to investigate.

The prosecution of the just completed 250 billion dong highway case shattered in Gia Lai - Photo 3.

More than 100 m of road have sunk

Speaking with the Nguoi Lao Dong newspaper reporter on November 7, the PMU 6 representative said that next week he will meet with the relevant units to implement corrective measures according to the plan established by the Ministry of Transportation. Specifically, the subsidence road was inspected, the geology reassessed, and a new design plan developed.

“The construction unit will reprocess the foundation, reinforce the soft soil layer underneath and complete the construction. In this new plan, the elevation will be lowered, not the old one” – PMU 6 representative said.

Previously, as the Nguoi Lao Dong newspaper reported, the route that passed through the Ho Chi Minh Highway, passing through Chu Se district, Gia Lai province, was built from May 2018 to March 2019, completed. The highway is almost 11km long, including 3 tender packages with 4 construction units. The total investment of the highway is 250 billion VND. Although the road has not been delivered, it has been seriously damaged, the road surface of more than 100 meters has been broken, sunk and cracked. Location damaged by construction JSC 471 (Nghe An).