In October 2015, the Khanh Hoa Provincial People’s Committee and VCN Investment Joint Stock Company (abbreviated VCN Company) signed a BT contract for the project of Highway 4 (the section of Highway 6 – 23), west of the Le Hong street. Phong, Nha Trang city, with a length of more than 3.1 km, investment capital of 200.9 billion.
Making 3.1 km of roads, changing more than 6 hectares of “golden land”
In March 2020, the Khanh Hoa Provincial People’s Committee issued a decision to adjust Decision No. 2094, the value of assets formed through investment in 2017 was VND 211.7 billion, to 205.7 1 billion VND, 6 billion VND less. Because the airport land fund is unable to carry out BT’s agreement for the highway No. 4 project, VCN proposed to take other land for the settlement.
In June 2020, the VCN company sent a written request to the People’s Committee of Khanh Hoa province to pay the land fund to reimburse the BT project of Highway No. 4 with a land of more than 6 hectares in the warehouse from Binh Tan Port (Vinh Nguyen District, Ha Trang City). After that, the Khanh Hoa Provincial People’s Committee held a meeting to pay the value of the investment in the construction of road No. 4 in the form of BT to the VCN company.
Accordingly, the Khanh Hoa Provincial People’s Committee agreed on the policy to allow the review and study of the mentioned land, to make a land fund to pay the value of the investment in road construction No. 4. At the same time Keep in mind the investment project. Construction on this land must be in accordance with the provisions of the law and have all technical and social infrastructure works.
|
Attachment “public – private”
And yet, according to the project design, Highway No. 4 has the widest road section of 22.5m, in which the vehicle runs 10.5m (5.25m / lane), curb 12m (6m each side). The purpose of the No. 4 highway project is to contribute step by step to complete and complete the transportation infrastructure system of the new urban area west of Le Hong Phong Street (Phuoc Hai District, Ha Trang City), and at the same time connect the interconnection. across the network to reduce the burden of traffic congestion. However, in fact, when it was put into operation, highway n. 4 has become the most expensive road in western Nha Trang urban areas when the price of land on both sides of this road is around 30-40 million VND / m2.
The purpose of the construction of highway n. 4 to connect interconnected by network is to reduce the traffic congestion load for the area, especially Le Hong Phong route, but due to the narrow firm (10.5m), the Traffic on Highway No. 4 appeared frequently . |
Strangely, the highway n. 4 traverses 2 urban areas VCN Phuoc Hai and VCN Phuoc Long 1 urban area invested by VCN Company (!?). Khanh Hoa’s public opinion questioned: Why does the BT project go through urban areas of real estate companies, including the VCN company, but use the public budget to implement it? Real estate companies have to invest in the infrastructure system in that urban area, but why does Khanh Hoa province take public land (Binh Tan port warehouse) to repay infrastructure investment? of them, what specifically is 4th street?