The Bay Hien crossing (Tan Binh district, Ho Chi Minh city) has the support of people, agencies, schools … to clean, deliver the soil to start the construction of subway line 2 – Photo: TRUNG TRUNG
Few people know that many relocated households quickly agreed to hand over the site to implement the Ben Thanh – Tham Luong subway line 2 project soon.
“Many supporters must work quickly for the development of Ho Chi Minh City. Some people saw that the neighbors were struggling and did not clear up and they themselves mobilized the neighbors to deliver them early so that the landscape of the neighborhood was beautiful, avoiding the cleft of the house.
MR LE VAN KHOA
Quick consensus for key projects
Early in the morning, the section of Truong Chinh – Cach Mang Thang 8 street near the Bay Hien intersection passing through District 4 and District 11 (Tan Binh District, Ho Chi Minh City) was noisy with the sound of excavators and house demolition.
On both sides of the road, many houses were simply stretched out, bricks and stones strewn about. The car that carried the bar continuously in and out quickly cleaned the floor to prepare it for delivery. Many houses were demolished, leaving part of the land under renovation to stabilize their lives.
The Metro No. 2 project has started slowly for a long time, after many years of waiting, many people here and passing through this area begin to feel that the project is moving “cake” with people demolishing their own houses. site delivery.
Ms. Tran Thi Bach Dao – house number 13 Truong Chinh (District 11, Tan Binh district) – and her daughter opened a grocery store, their house had to go back almost 10 meters deep.
Ms. Dao has added a small table to the area of the dismantled house near the semi-temporary road surface: “In the past two months, the demolition of the house has slowed down the business, hoping the project will work quickly, workers freeze, At that time, we could negotiate the same “.
Ms. Dao is one of the families who agreed to quickly deliver the house for the metro project No. 2. The house measures 88 mtwo 48 m after demolitiontwo, his family managed to live. Ms. Dao shared listening to the 2012 project, repeatedly invited to meetings, announced the dismantling but many years It does not move.
Like many other projects, displaced people initially disagreed with the price of compensation. Many meetings and meetings between the government and the people are simply about negotiating prices.
Ms Dao herself disagreed with the first compensation price offered in 2017 because her residence area was only compensated with 104 million VND / m2.twoWhile recently, the Bay Hien intersection towards District 1 (about 300m from Ms. Dao’s home – PV), the compensation price is up to 134 million VND / mtwo.
By 2020, the compensation price will increase to 150 million VND / mtwoAlthough still lower than the market price, she and her husband quickly agreed on their thoughts.
“The people of the project speak, they only claim benefits, compensation prices, but they have no opinion on the policy. But they can’t keep asking, after all, this is also a key road project, after completing me. It also benefited, so my family quickly agreed, ”shared Ms. Dao.
Ms. Hua Thi Thien Huong’s family – No. 1220 Cach Mang Thang 8, (District 4, Tan Binh District) – also received money for the workers to demolish the house part of the No. 2 subway project. But now it temporarily suspends waiting for workers to clean the facilities and then reopen the sale.
Ms Huong said that although the compensation price was not as expected at first, she thought the project would work quickly later, the road to expand her house also had an advantage, so she soon agreed to deliver the site.
A house on Truong Chinh Street (Tan Binh District, Ho Chi Minh City) was demolished and handed over by people – Photo: TRUNG TRUNG
“It doesn’t matter, eat a lot as “
A project that spans more than 11 km with more than 600 homes demolished part or all of their homes, although most agree, many homes are struggling to find ways to stabilize their lives. Many families, even though they have received money, still have difficulties knowing where to live and where to work.
The people in the subway project n. 2 for a long time on the facade have lived mainly on business, find a home should be more deliberate. more deliberate.
For the past 3 months, Mr. Pham Phan Phuoc Hai’s family – No. 23 Truong Chinh (District 11, Tan Binh District) – although they agreed, only waiting for the papers sent by his uncle from abroad will hand over the house , but the family His family couldn’t help but worry about the life ahead.
Mr. Hai’s house is 40 meterstwo, when it was demolished only 1.2 mtwo, not qualified to live to relocate. Mr. Hai’s family has worked as a drug dealer for more than 50 years, so many clients who know the house have to go elsewhere to rebuild from scratch.
What worries you most is that it is very difficult to find a house with a facade equal to the size and close to your area of residence.
Mr. Hai honestly said, “I agree with the policy of relocating the project, but at the current price, it is difficult to go elsewhere to buy a house with a similar facade.” Outlying neighborhoods to buy houses, rebuild from scratch. “
The family of Ms. Tran Nguyen Anh Tuyet, 58 Truong Chinh (Hall 4, Tan Binh District), also received the money, but hesitantly asked to stay longer to arrange accommodation.
Ms. Tuyet’s house is about 40 meters wide.two, if demolished only about 11 mtwo. If the home is in good condition, a few years ago he decided to buy another place when the price of the house was still low, but since his family did not have enough conditions, he was only waiting for compensation.
Now receiving almost 5 billion dong in compensation, looking to buy a house near the old house is also difficult, but due to the general policy, she told herself: “Never mind, eat a lot. as soon as “.
Ms. Tran Nguyen Anh Tuyet (House No. 58 Truong Chinh, District 4, Tan Binh District, Ho Chi Minh City) said that her house will recede by up to 10 m – Photo: TTD
End of the year transfer all the premises
Mr. Nguyen Tan Tai – Head of Compensation and Site Cleaning Board of Tan Binh District – said that the district had 324/356 households that relocated subway project No. 2 agreed to receive compensation. After receiving money for a month, people will hand over the premises.
According to Mr. Ti, the No. 2 subway project passing through Tan Binh has 6 stations, of which 2 stations were delivered in June 2020, it is expected that in September 2020, the district will deliver the land of 3 stations plus. Bay Hien, Nguyen Hong Dao, and Ba Queo. And the Pham Van Hai district station continues to campaign to strive to deliver the facilities. in the fourth quarter of 2020.
Regarding resettlement, people were selected for 3 apartments: Bau Cat, Tan Tru (Tan Binh district) and Tan Thoi Nhat (district 12). If people don’t buy an apartment, the city will support an additional 5% of the land value so they can find a new home.
Tan Binh district has 57 households eligible for resettlement, but around 50 households choose to keep cash, the remaining 7 households are considering choosing a resettlement plan. In addition, entrepreneurs can prove that they have paid taxes and can verify their income for 3 consecutive years Event calculator support.
Speaking with Tuoi Tre, Mr. Le Van Khoa – Director of Project Management Unit 2 (HCMC Urban Rail Management Board) – said that the investor has received the facilities of some stations, such as stations. S10 – Pham Van Bach, S11 – Tan Binh (Tan Binh district); Terminal S5 – Le Thi Rieng (District 10).
Yesterday, August 28, the investor also checked the field to hand over the station site in Tan Phu district.
“With the high consensus of the people, the ground clearance of the subway line is expected to be finished by the end of this year,” said Mr. Khoa.
According to Mr. Khoa, for the project to work quickly, there must be the consensus of the people, as well as the preparation and politics of the city. The experience of the No.1 metro project when ground clearance has not been completed has resulted in huge costs incurred. Therefore, with the No. 2 metro, the city has a policy to complete the land before awarding the contract to the contractor.
The city has attributed the responsibility of the leader to two metro lines, of which line 2 is the focus of the clean-up work at the site.
“In the second week of each month, the leaders of the Ho Chi Minh City Party Committee invite all related units to quickly meet to solve problems. Every two weeks, the leaders of the City People’s Committee meet to review progress and problems and fix them on the fly there, “said Mr. Khoa.
Don’t let people suffer
According to Mr. Le Van Khoa, Ho Chi Minh City guided the expedited clearance, but with consensus, agreement of the people, determined not to let the people suffer. The city flexibly arranges resettlement houses in good locations for residents and requires the correct calculation for individuals for 2020 unit prices.
The Government also agreed to the City’s request to restructure an additional 520 billion dong (including provisions) to update the actual unit price to compensate the people.
Line 2 of the metro has a length of 11,042 km, passing through districts 1, 3, 10, 12, Tan Binh, Tan Phu with 2 km of overhead and more than 9 km underground, with 11 stations. The project has more than 600 affected homes with a total compensation area of more than 250,000 square meterstwo.