Related to the treatment of the building 8B Le Truc (Ba Dinh District, Hanoi City – Building Investor is Le Truc Garment Joint Stock Company) On December 10, the Ba Dinh District People’s Committee handed over the building to the investor for completion and delivery. resident apartments.
Inside the 8B Le Truc building, many apartments have basically been completed – Photo: QP
According to the investor’s representative, after receiving the building, the investor has concentrated resources to complete the rest of the items, handing over the apartment to the buyer before Lunar New Year 2021. After the forced 18th floor, the investor is still waiting for the approval of the plan of specialized units of the city of Hanoi. Currently, the interior equipment of the apartment has been demolished on the demolished floors.
As for the floor plan of the house for those who buy apartments on the 18th and 19th floors was demolished, the investor representative said that the 19th floor completed the execution more than 4 years ago, so the agreement with the buyers consummated. As for the buyer of a house on the 18th floor, the investor offers 3 options: buyers can choose another apartment in the pool of unsold apartments in building 8B Le Truc; 2 is a home buyer receiving an apartment in another project from the investor; 3 is the investor to reimburse the purchase of the house to the clients if they cannot agree on the first two options.
The workers carried out the removal of the wrong part before the government handed over the building to the investor
Previously, in late November 2015, the city of Hanoi allowed functional forces to “cut off the top” of the 8B Le Truc building. At the end of 2016, the entire attic and the 19th floor of the 8B Le Truc building were completely demolished. However, from 2016 to mid-2020, new functional forces continue to demolish the 18th floor of the building.
In early November 2020, the City of Hanoi informed the Prime Minister of the results of the handling and overcoming of the building order violations at the 8B Le Truc building.
After 6 months of construction, the city of Hanoi has finished demolishing the 18th floor of the 8B Le Truc building. The beams on the 18th floor of the 8B Le Truc building are preserved to ensure that the supporting structure of the building is not affected long after application. After the demolition of the 18th floor, the concrete slabs were moved, the workforce dismantled the crane tower installed in the house of 8B Le Truc from May 2020. Safety nets during the demolition of the 18th floor of the building 8B Le Truc will be retired during the completion of the project.
BHThanh