Good news for Istanbul! Sabiha Gökçen-Kadıköy Airport will be connected without interruption



[ad_1]

“91 PERCENT OF THE CONSTRUCTION ACTIVITIES CARRIED OUT”

The Minister of Transport and Infrastructure Karaismailoğlu stated that they have completed the excavations in the construction of the tunnel of the line as of today, and that the concrete production of the tunnel and the inner lining of the project, as well as the reinforced concrete station and the finishing work continues.

Karaismailoğlu indicated that railway works and electromechanical manufacturing have also started, and provided the following information:

“To date, we have excavated 15,970 meters of tunnels on our line. We pour more than 90 thousand cubic meters of concrete. 73 percent of the 14,536 meters of railway installation work, that is, 10,674 meters. And it is time to start the first railway resource. Project cost 2 billion 369 “The advance of the line, which is millions of lire, in construction activities is 91 percent, and the advance in electromechanical works is at the level of 20 percent. With the completion of our metro, the total of our economic profits in 2021-2045 will be 181 million 297 thousand euros ”.

CONSTRUCTION OF 5 METRO LINES CONTINUES

Minister Karaismailoğlu, “Pendik-Tavşantepe-Sabiha Gökçen Airport”, “Bakırköy Coast (IDO) -Bahçelievler-Güngören-Bağcılar Kirazlı”, “Başakşehir-Çam Sakura-Kayaüşehir Airport”, Istanbul Kemerküekgaz “Kımeçehir Airport, Kımeçekgaz lines” -Kımeçekgaz Airport -Başakşehir-Arnavutkoy-Istanbul Airport “continues.



[ad_2]