The founding of the Rize-Artvin Airport, which was started in an area of 766 hectares by the Ministry of Transport and Infrastructure in Yeşilköy, in the Pazar district of Rize, and then increased to 1000 hectares by increasing the filling quantity, on 3 April 2017, by President Recep Tayyip Erdoğan. was released. Sea filling continues in the area where materials are trucked day and night to the airport. In addition to trucks, 2 earthmoving boats are also used on the works. In the construction of the airport, where approximately 120 thousand tons of filling are carried out per day, the process of filling the runways continues. Stones trucked from Kanlımezra, 3 kilometers from the project site, and the Tektaş quarries, 7 kilometers away, are dumped into the sea via a connecting road.
class = “cf”>
3 MILLION PASSENGERS WILL BE TRANSPORTED PER YEAR
Stones filled by trucks on digging boats are thrown into the sea at a depth of 25 to 30 meters in the open air. The interior area of the breakwater will be approximately 2 million square meters and a total of 2.4 million square meters of sea fill will be made. At the project, where 80 percent of the landfill was completed, work began on the runway, apron and taxiway areas. The Rize-Artvin airport infrastructure works, which are expected to use 3 million passengers a year, will cost 1 billion 78 million lire.
GOVERNOR ÇEBER: THERE WILL BE A TEA MUSEUM IN THE TERMINAL
class = “cf”>
Rize Governor Kemal Çeber stated that it was decided to be a tea glass figure in the construction of the airport tower, saying: “Activities at the airport were not interrupted, including the period of the pandemic. It was only updated working hours due to the pandemic. We said ‘health first’ and updated the business schedule. In the meantime, we made some additions and improvements to the airport. Hopefully our citizens of Rize, Artvin and Black Sea will start using the airport in these months next year. We attach great importance to local architecture in the upper structure of the airport. According to him, the project has been reconsidered. By changing the base of the superstructure, there have been changes that incorporate the characteristics of the Black Sea. I hope that we have an airport terminal that highlights much more the silhouette of our region. The hand will be an aesthetic field. I hope that we will present the world brand of Rize tea there in the best possible way. anera “.
‘WE HAVE REACHED 80 PERCENT’
class = “cf”>
Governor Çeber said: “Our work continues very fast. When we kept the upper structure separate, we got closer to 10%. We were waiting for them to sit there. We were going a little slow, now we will arrive much faster. Tea when you go to the area. You will see that our tower is shaped and our terminal building is becoming visible little by little. I hope that the people of the Black Sea Region have met with Rize-Artvin Airport and started receiving service around this time next year. ” , He said.
‘THE AMOUNT OF FILLING INCREASED’
Governor Çeber stated that the amount of stone fill in the planned area was increased to 100 million tons and said: “Our airport will have a capacity of 3 million passengers. A large proportion of this will be direct flights from abroad. The The first place people will see Rize and the geography of the Black Sea will be the airport. We asked our minister and minister to assess this issue separately. We wanted another 600 acre area suitable for filling next to the airport to be added to the landfill , which corresponds to 15-20 million tons. This place fully reflects the social and cultural characteristics of Rize, and those who land at the airport will meet Rize first. and we wanted the deceased to be the area that we would equip to be the last point Rize’s view.