On the signs posted by IMM at the Ataköy / Şirinevler metrobus stop and at the metro station here, “As of September 11, 2020, the M1 line will be closed for operation due to construction works between the airport stations. Ataköy / Şirinevler-Atatürk within the scope of the renovation project, and transportation will be provided by free ring bus services. Thanks for your patience and understanding.
The Yenibosna and World Trade Center (DTM) -Istanbul Expo Center stations, which lie between them, will not be used after the Ataköy / Şirinevler and Atatürk Airport metro stations are out of service.
According to the IMM statement, “The Ataköy-İkitelli subway line, which is under construction, is being integrated into the existing subway at Yenikapı – Atatürk Airport and at Yenibosna Station. Due to construction works on the Yenikapı Airport – Atatürk transfer, the metro services of the M1A Yenikapı-Atatürk Airport line. The period will run between Yenikapı – Ataköy / Şirinevler. A bus will serve Ataköy-Şirinevler, Yenibosna, World Trade Center and Atatürk airport stops. ” It was said.
According to the statement made by IMM, an underground pedestrian road connection will be built to the Yenibosna station of the current M1A Yenikapı – Atatürk Airport metro. When the integration works are completed, a convenient and fast transfer between the M1A Yenikapı-Atatürk Airport and M9 Ataköy-İkitelli lines will be provided. There will be uninterrupted transportation between Yenikapı and the İkitelli region with a single transfer by rail system.
In the construction process of the project, which is expected to last around 14 months; The Yenibosna, World Trade Center and Atatürk Airport stations will be closed. Passengers wishing to continue in the direction of Atatürk Airport can use the IETT buses at the Ataköy / Şirinevler station exit free of charge. The shuttle bus service will serve the stops at Ataköy-Şirinevler, Yenibosna, World Trade Center and Atatürk Airport.
ABOUT THE M9 ATAKÖY-İKİTELLİ METRO LINE
When the 13.4-kilometer line consisting of 12 stations is completed, the partial opening of which is scheduled for 2021; It will reduce the distance between Ataköy and İkitelli to 19.5 minutes and will have a capacity of 35 thousand passengers per hour in one direction.
Line; Bakırköy-Kirazlı – Başakşehir Metro at İkitelli Industrial Station, Kabataş – Mecidiyeköy Metro – Mahmutbey – Esenyurt at Mehmet Akif Station, Kirazlı – Halkalı Metro at Mimar Sinan Airport Station, Yenikapı Airport – Metro Station del Atatürk at Yeniboskörk station will be integrated with Marmaray.