Look back at the Orange Line conflict before bidding !!



[ad_1]

Pursuing the orange line schedule before “bidding,” the NACC calledThe song is waiting for you !!

Lee Lung Tungnang for several months. To tender for the MRT Orange Line project During Bang Khunnon – Min Buri (Suwinthawong) that MRTA opened for private investment in western construction Install, supply all electric train systems AND receive the concession to operate the 35.9 kilometer route (km) for a period of 30 years with a total amount of approximately 1,200 million baht

Finally, on February 3, 2021, the match turned after the selection committee. It is resolved to approve the cancellation of the tender for the Orange Line. Which is an ongoing consideration of the Board of Directors. They have given guidance That if within 1 month it has been postponed to open the envelope and there is no conclusion OR there is a delay That will have an impact on the implementation of the project. Currently, more than 1-2 months have passed, but there is still no progress. Therefore, the resolution was approved and seen as a way to produce results clearly. And it does not affect operations anymore

Matichon Online compiled this project timeline Happened since July 3, 2020, the Mass Rapid Transit Authority of Thailand (MRTA) issued an announcement to private companies interested in investing in this electric train project. Documents can be purchased to participate in the auction from July 10 to July 24, 2020, dividing the investment period as follows:

Phase 1 Design and Construction of Civil Works And the acquisition of the train system is divided into 2 parts: Part 1. Design, acquisition, manufacture, installation, testing of the electric train system. And test the running of the Eastern Project train (Thailand Cultural Center – Suwinthawong) for 3 years and 6 months

Part 2: Design and Construction of Civil Works and Design, Procurement, Manufacturing, Installation, Testing of Electric Railway Systems and Experimentation for Western Projects (Bang Khunnon – Cultural Center of Thailand) for a period of 6 years

Phase 2: Operation and maintenance service for a period of 30 years from the start of the service for the Metro del Este Project.

After that, on September 17, 2020, Bangkok Mass Transit Public Company Limited or BTSC petitioned the court to order the MRTA and Selection Committee. Go back to the rules, conditions, new bidding documents (TOR), not the new rules that have been changed after the closing of the bidding envelope.

On September 24, 2020, Bangkok Mass Transit Public Company Limited sent a letter to Anti-Corruption Organization (Thailand) to such cases

Later, on September 28, 2020, Mr. Srisuwan Chanya, Secretary General of the Association of the Constitutional Protection Organization of Thailand Report to the Cases of the Department of Special Investigations (DSI) received a complaint that Selection Committee under the Joint State-Private Investments Act 2019 (Section 36) for Bang Khunnon – Minburi (Suwinthawong) Orange Line Metro Project resolved on August 21, 2020 to change TOR

After finding a suspicious question, for example, the technical package will be split if it meets the criteria Therefore, it will open the financial envelope accordingly But this contest brings back the envelope technique to calculate the score with the financial envelope a rating of 30/70, if someone has the highest total score, they will be selected. And at the committee’s discretion. This can lead to fraud like never before, so DSI must be investigated.

On October 14, 2020, it was reported that the Central Administrative Court will schedule a hearing in the event that BTSC has filed a lawsuit against kg. The Joint State-Private Investment Law of 2019 (Section 36), the Orange Line Project, the Bang Khun Non – Min Buri Section (Suwinthawong) and two people together, requesting that the resolution be revoked. Selection. In case of modification of the conditions of the TOR, offer technical proposals to qualify together with price proposals. After the sale of the auction envelope has been closed.

On November 4, 2020, the Association of Journalists and Media (Thailand) and the National Network of Anti-Corruption Media (NACC) filed a complaint with the Office of the National Anti-Corruption Commission (NACC) requesting that the Governor of the MRTA and the Selection committee. On the Orange Line project Giving the same reason as BTSC

Later, on January 26, 2021, MRTA Governor Mr. Phakaphong Sirikantaramas revealed the progress of private selection to invest in the Orange Line MRT project. Civil works during the Cultural Center – Bang Khunun AND operating the entire route During Bang Khunnon – Minburi (Suwinthawong), indicating that the MRTA is still waiting to hear the decision of the Administrative Court. After the private right to lodge a complaint with the court And before this, the court had scheduled an investigation.

And it is expected to be considered as soon as the MRTA has been opened to accept the proposal envelope from late last year. Therefore, it is considered that the process has been delayed a little, but it is estimated that if the judicial decisions It will be able to accelerate the process of consideration of proposals so that the implementation remains as planned Open for service in 2024

This is the last interview of the Governor of the MRTA before the Selection Committee. It is resolved to approve the cancellation of the tender for the Orange Line.

You should continue to follow that. What criteria will the MRTA use in the tender? And will it repeat the same brand or not? Next !!