Major General Asawin Kwanmuang Governor of bangkok After chairing the BMA management meeting on November 16, 2020, the progress of the preparation for the opening of the Green Line train extension, Mo Chit – Saphan Mai – Khu Khot, full system, was revealed. Than from the test results of walking the BTS Expanding the rest From Wat Phra Si Mahathat station to Khu Khot station, there were no problems. Which, as originally scheduled, will open for service on December 16
However, there may be changes due to BTSC, the operator of the Green Line train extension, Bearing – Samut Prakan. And Mo Chit – Saphan Mai – Khu Khot period has made a claim letter for the train salary, which began to gradually open to service from 2018 onwards to the present, worth more than 8,000 million baht. Threatening to stop running the service
Major General Asawin Accept that now Bangkok there is no money to pay I have to ask the government for support Because the government gave Bangkok responsible for the bus And the open part does not charge a fee
Major General Asawin said the Gold Line Phase 1 testing progress, Krung Thon Buri Station – Khlong San District Office Station Is OK May open for service as scheduled on December 16, of course. the prime minister is the open president However, such a project Bangkok has given Bangkok Thanakom Company Limited or KT to operate, which does not use the government budget. But using the anticipated income from the ad space right on the train to invest in construction. What is a way to seek cooperation with the private sector Therefore, the project can be completed as quickly as possible and there is no need to wait for the budgeting process. Government sector and ownership in the project is also owned by Bangkok
[ad_2]