Reporter reports the share prices of Super Energy Corporation Public Company Limited or SUPER The latest at 2:55 pm is 0.81 baht, plus 0.04 baht or 5.19%, the highest at 0.83 baht, the lowest at 0.78 baht, with a trade value of 290, 92 million baht.
Mr. Jomsup Lojaya, Chairman of the Board of SUPER, revealed that the company expects annual revenue to reach 10 billion baht as a result of revenue recognition from solar power plant projects in Vietnam. 550 megawatt capacity throughout the year After commercial distribution (COD) is expected to start in late November 2020, SUPER currently has approximately 900 MW of power plants in Thailand and Vietnam in COD.
Meanwhile, another 421 MW of wind power projects in Vietnam are expected to start at COD in 1Q21, 50 MW in the first phase, 50 MW in 2Q21 and the remaining 321 MW at COD. Beginning of quarter 4/64
For this year’s revenue direction The company believes there is an opportunity to exceed the 6.800-7 billion baht target of over 900 MW revenue recognition from all COD projects, including the start of project revenue of power plants. The sun in Vietnam With a capacity of 550 megawatts in November too
At the same time, the company continues to seek new investments. Both projects in Thailand, Vietnam and other countries To support future growth to make it stable Will focus on projects that have a return on investment in accordance with the equity participation ratio (EIRR) not less than 13-15% to provide good returns to investors.
The performance trend in 2020 is expected to continue to grow from the previous year. And get a chance to set a new record. It was driven by the recognition of commercial power sales (COD) revenue from the two existing power plants. And new power plants both at home and abroad Especially from solar power plant projects in Vietnam. The total production capacity of 550 megawatts, COD will be phased out in December 2020 according to the planned schedule. And it will support a significant growth While the wind power project (Eolic Park) with an installed capacity of 171 megawatts and 250 megawatts in the process of accelerating construction and is expected to gradually COD within the next year.