Because the night construction work at the Zurich-Hardbrücke station could not be completed on time, there are still changes in the S-Bahn traffic.
At the Zurich-Hardbrücke train station, major maintenance work is underway overnight. Among other things, the points are replaced. This work could not be completed on Monday morning before the S-Bahn began operating and, as of 11 a.m., is still in progress, as announced by an SBB spokesperson upon request. Also in 14 The reasons for the delays are unknown.
This, in turn, has consequences for rail traffic. Five S-Bahn lines are affected, there are delays, various failures and detours:
So he held the S12 not at the Hardbrücke, but also not at Stettbach and Stadelhofen train station. It detoured through Oerlikon and stopped at the main station Löwenstrasse station.
the S15 it was delivered in Zurich and was canceled between HB and Glattbrugg.
the T16 The direct connection between Zurich-Tiefenbrunnen and the airport was canceled, so he only drove from the right bank of Lake Zurich to Tiefenbrunnen.
They are also affected S3 Y S7.
The outage should last until 3 pm, SBB announced at 2 pm “SBB regrets the inconvenience and apologizes to the affected travelers,” writes the SBB spokesperson. The current situation may via online rail traffic information can be accessible.